Hangmuren- und Murgangschutz - Borusan EnBW 2019

18 meters top width require strong GEOBINEX ropes

Hangmuren- und Murgangschutz - Borusan EnBW 2019

8 meters long wire rope anchors placed in 92 mm bore holes - anchoring in solid rock is required to resist the enormous forces of debris and mudflows

Hangmuren- und Murgangschutz - Borusan EnBW 2019

Final control of the VX160-H6 ringnet barrier

 

Systeme

 

Systemlänge

15 m

 

Installationsjahr

2019

Ausgangslage

At the hydro power plant infrastructure in 2011 and 2017 torrents brought down debris and clogged culverts of the draining system.  Around 5'000 m³ of debris damaged the HPP area.

Massnahme

At the ideal place for this debris flow barrier, there also is an area for debris material nearby. The system is a V-shaped, 6 meters high barrier (VX160-H6) with 8 meters deep wire rope anchors.

Land/Region

Türkei

Kunde

Borusan EnBW

Planer

Geobrugg AG

Ausführende Firma

Artusa Geohazard

Geschützte Objekte

Sonstige

Korrosionsschutz

GEOBRUGG SUPERCOATING

Ansprechpartner

Kevin Coyle
 

Kevin Coyle

Regional Manager Northeast

Naturgefahren
Uferschutz/Wasserbau
Geobrugg North America, LLC,3 Beaudet Terr,CT 06237 Columbia / USA Regional Manager Northeast

E-Mail

Saleh Feidi
 

Saleh Feidi

Naturgefahren
Uferschutz/Wasserbau
Geobrugg North America, LLC,8921 Emperor Ave.,91775 San Gabriel, California / USA

E-Mail

John Kalejta
 

John Kalejta

Naturgefahren
Uferschutz/Wasserbau
Geobrugg North America, LLC,KS 67226 Wichita / USA

E-Mail

Bob Lyne
 

Bob Lyne

Naturgefahren
Uferschutz/Wasserbau
Geobrugg North America, LLC,8004 Windspray Drive,NC 27358 Summerfield / USA

E-Mail

Pierce Runnels, Civil Engineer
   

Pierce Runnels

General Manager Geobrugg North America

Naturgefahren
Geobrugg North America, LLC,22 Centro Algodones,NM 87001 Algodones / USA , Civil Engineer General Manager Geobrugg North America

E-Mail

Tim Shevlin
 

Tim Shevlin

Naturgefahren
Geobrugg North America, LLC,OR 97302 Salem / USA

E-Mail