Steinschlagschutz - Ten West Link 2022

Rockfall barriers protecting the transmission line towers.

Steinschlagschutz - Ten West Link 2022

Lateral view of the rockfall barrier

 

Systeme

 

Systemlänge

- 230 m

 

Installationsjahr

2022

Ausgangslage

The Ten West Link project is a new power project from Southern Arizona & California. The project goes across the Eagletail Mountains & Wildreness, where transmission line towers will be built.

Massnahme

Geobrugg was tasked with providing ten GBE-100A-R rockfall barriers to protect ten transmission line towers that will be built. The barriers are three meters high with a total length of 230 meters.

These barriers will protect personnel, roadway and future transmission lines. This particular transmission line will span 125 miles connecting Arizona and California, improving transmission system efficiency and reliability.

Thank you Adams Contracting for the pictures. 

Ausführende Firma

Geschützte Objekte

Strasse, Infrastruktur

Korrosionsschutz

Verzinkt

Ansprechpartner

Roger Moor
   

Roger Moor

Country Manager Ost- und Zentralschweiz, Liechtenstein

Naturgefahren
Uferschutz/Wasserbau
Minen / Bergbau / Tunnel
Geobrugg AG,Aachstrasse 11,8590 Romanshorn / Schweiz Country Manager Ost- und Zentralschweiz, Liechtenstein

E-Mail

René Müller
   

René Müller

Country Manager Kantone AG BE BL BS FR GE JU NE SO VD VS

Naturgefahren
Uferschutz/Wasserbau
Minen / Bergbau / Tunnel
Geobrugg AG,Industriestrasse 21,5200 Brugg / Schweiz Country Manager Kantone AG BE BL BS FR GE JU NE SO VD VS

E-Mail

Alexander Bittendorfer
   

Alexander Bittendorfer

Project Manager Inspection Services

Naturgefahren
Geobrugg AG,Aachstrasse 11,8590 Romanshorn / Schweiz Project Manager Inspection Services

E-Mail

Isacco Toffoletto
   

Isacco Toffoletto

Ticino Country Manager

Naturgefahren
Uferschutz/Wasserbau
Minen / Bergbau / Tunnel
Geobrugg AG,Stabile Cometal, via Pizzante 7,6595 Riazzino / Schweiz Ticino Country Manager

E-Mail