Böschungsstabilisierung - Schmerikon State Road 17 2013

Bird's eye view of the protected objects: State roadway, railway, bicycle path, building and port

Böschungsstabilisierung - Schmerikon State Road 17 2013

Slope failure seen shortly after the emergency work began a few days after the incident in June 2013

Böschungsstabilisierung - Schmerikon State Road 17 2013

Spider excavator during drilling

Böschungsstabilisierung - Schmerikon State Road 17 2013

Drilling along the top edge of the failed slope

Böschungsstabilisierung - Schmerikon State Road 17 2013

Drilling with manual equipment

Böschungsstabilisierung - Schmerikon State Road 17 2013

View of the upper section showing nailed TECCO G65/3, P33 spike plates and border rope

Böschungsstabilisierung - Schmerikon State Road 17 2013

Lage: Zürichsee, Schweiz Bundesamt für Landestopographie, Bern, Schweiz Landeskarte 1:50'000

 
 

Installationsjahr

2013

Ausgangslage

In the first days of June 2013 heavy storms and intense rainfall hit the region of the upper lake of Zurich. Due to saturation of the ground and instable geological conditions, a landslide buried a long section of heavily travelled commuter roadway and railway along the lake. This landslide caused complete closure of the infrastructure.

Geologie

Top Section: weathered marl

Bottom section: weathered sandstone / siltstone

Massnahme

The department for underground construction initiated re-establishment and sustainable prevention of future similar incidents a few days later. To reach a quick decision and accelerate the construction, the department quickly involved local and regional partners.

Solutions discussed were rockfall barrier, manifold, or anchored TECCO® System the most favorable and ultimately chosen solution.

The upper slope section (marl) was protected and stabilized using a nailed mesh. The lower sandstone/siltstone section was covered with a drape to ensure that falling debris is kept close to the slope while being guided and deposited to the ditch.

Kunde

Kantonales Tiefbauamt, Kanton St.Gallen, Switzerland

Ausführende Firma

Oberholzer Bauleistungen Inc., Neuhaus, Switzerland

Geschützte Objekte

Strasse, Eisenbahn, Infrastruktur

Korrosionsschutz

GEOBRUGG SUPERCOATING

Planer

Dr.A.Gübeli Inc., Jona, Switzerland

Ansprechpartner

Roger Moor
   

Roger Moor

Country Manager Ost- und Zentralschweiz, Liechtenstein

Naturgefahren
Uferschutz/Wasserbau
Minen / Bergbau / Tunnel
Geobrugg AG,Aachstrasse 11,8590 Romanshorn / Schweiz Country Manager Ost- und Zentralschweiz, Liechtenstein

E-Mail

René Müller
   

René Müller

Country Manager Kantone AG BE BL BS FR GE JU NE SO VD VS

Naturgefahren
Uferschutz/Wasserbau
Minen / Bergbau / Tunnel
Geobrugg AG,Industriestrasse 21,5200 Brugg / Schweiz Country Manager Kantone AG BE BL BS FR GE JU NE SO VD VS

E-Mail

Alexander Bittendorfer
   

Alexander Bittendorfer

Project Manager Inspection Services

Naturgefahren
Geobrugg AG,Aachstrasse 11,8590 Romanshorn / Schweiz Project Manager Inspection Services

E-Mail

Isacco Toffoletto
   

Isacco Toffoletto

Ticino Country Manager

Naturgefahren
Uferschutz/Wasserbau
Minen / Bergbau / Tunnel
Geobrugg AG,Stabile Cometal, via Pizzante 7,6595 Riazzino / Schweiz Ticino Country Manager

E-Mail