Mar del Plata - Quarry

Avenida de los Trabajadores, B7603HYI, Mar del Plata, Argentinien
2020
Ausführende Firma
Geschützte Objekte
Infrastruktur
Korrosionsschutz
GEOBRUGG SUPERCOATING
Stabilisierte Fläche
540 m²
Maximale Hanghöhe
20 m
Hangneigung
70 ° - 90 °
Ausrichtung
Süd-Ost
Weitere verbaute Anwendungen
Steinschlagschutz
Ausgangslage

The 9 de Julio thermal power plant is located in an old quarry, which emerged when rocks for the construction of the breakwaters of the city were extracted. The blasting of the rock left vertical slopes with a height of 20 meters - they show continuous rockfalls. A few meters from these slopes, there is a gas pipeline and a fuel oil pipeline feeding the boiler of this plant.

Geologie

Fragmented sandstone. 

Massnahme

After several rockfalls events and with the aim of preserving the integrity of these gas and fuel oil pipelines, a protection system was implemented. The closest 30 linear meters of slope to these pipelines were intervened, installing a drape system.

Ansprechpartner

Roger Moor
Roger Moor
Country Manager Ost- und Zentralschweiz, Liechtenstein
Naturgefahren, Uferschutz, Minen / Bergbau / Tunnel
Geobrugg AG
Aachstrasse 11
8590 Romanshorn / Schweiz
René Müller
René Müller
Country Manager Kantone AG BE BL BS FR GE JU NE SO VD VS
Naturgefahren, Minen / Bergbau / Tunnel
Geobrugg AG
Industriestrasse 21
5200 Brugg / Schweiz
Isacco Toffoletto
Isacco Toffoletto
Ticino Country Manager
Naturgefahren, Minen / Bergbau / Tunnel
Geobrugg AG
Stabile Cometal, via Pizzante 7
6595 Riazzino / Schweiz