Impact Protection - Chimney blasting Moorburg 2024

The high-tensile steel wire mesh is particularly suitable for blast protection of irregular-shaped components. It was adapted to the elements of the base construction on site.

Impact Protection - Chimney blasting Moorburg 2024

The two front supports were encased in a wooden construction and high-tensile steel wire mesh before being blasted.

Impact Protection - Chimney blasting Moorburg 2024

Surrounding buildings and infrastructure are thus protected from debris and shrapnel.

Impact Protection - Chimney blasting Moorburg 2024

Two of the four supports and other structural elements in the lower section of the towers were clad with steel wire mesh.

Impact Protection - Chimney blasting Moorburg 2024

Steel wire mesh as blast protection is easier and quicker to install than other materials.

 
 

Year of installation

2024

Initial situation

The Hamburg Energy Works GmbH had to create space for new infrastructure. As part of the decommissioning of the existing energy facilities, the chimneys of the former flue gas desulfurization plant were demolished.

The demolition company Hagedorn had to ensure that the existing infrastructure was protected from debris and splinters during the demolition.

Description

Extensive protective measures were necessary before the 2,300-ton and 130-meter-high chimneys fell onto the prepared fall bed. The two 20-meter-high supports that were demolished were entirely clad with debris protection mesh (TECCO® G65/4). A total of 770 m² of explosion protection mesh was installed.

The impressive demolition can be seen on the Hagedorn Unternehmensgruppe's YouTube channel.

Country/Region

Germany

Protected object

Infrastructure, Other

Your local contact

Ivo Naef
 

Ivo Naef

Sales Manager Safety Solutions

Impact Protection
Geobrugg AG,Trucks via road 14 or 13 only!, Aachstrasse 11,8590 Romanshorn / Switzerland Sales Manager Safety Solutions

E-Mail