Gore Quarry

LD8 2PL, Walton, Powys
2018
客户
Tarmac Ltd
工程
Key Geosolutions
承包商
Derbyshire Geotechnical
分包商
None
防护对象
Mine / Quarry
能级
500 kJ
系统的高度
3.0 m
系统长度
100 m
腐蚀保护
GEOBRUGG SUPERCOATING
其他安装的应用程序
矿井/隧道
情况

Planned extensions to the sandstone, Gritstone quarry required the extraction of overburden. Materials had the potential to travel down the outer edge of the site, down to the A44 road.

Key Geosolutions undertook rockfall analysis and calculated that a 500kJ and 3 metres high rockfall system would be required.

描述

Derbyshire Geotechnical contacted Geobrugg for advice on system types best suited for this location.

After an initial site visit, it was agreed that the GBE-500A would be the best option as the reduced post weight over that of the GBE-500A-R allowed for easier installation due to the limited access routes to the location.

The 100 m long system with post spacings of 10 m (11 posts) was secured with 2nr 4 m long threaded bars. Upslope and lateral anchors were 6 m long threaded bars fitted with Geobrugg flexheads.

本地联系方式

Roger Moor
Roger Moor
Country Manager Ost- und Zentralschweiz, Liechtenstein
自然災害防護, Coastal Erosion Protection, 矿井/隧道
Geobrugg AG
Aachstrasse 11
8590 Romanshorn / 瑞士
René Müller
René Müller
Country Manager Kantone AG BE BL BS FR GE JU NE SO VD VS
自然災害防護, 矿井/隧道
Geobrugg AG
Industriestrasse 21
5200 Brugg / 瑞士
Isacco Toffoletto
Isacco Toffoletto
Ticino Country Manager
自然災害防護, 矿井/隧道
Geobrugg AG Ticino
Stabile Cometal, via Pizzante 7
6595 Riazzino / 瑞士