Proteção contra desprendimentos - Gore Quarry 2018

Completed GBE-500A installation

Proteção contra desprendimentos - Gore Quarry 2018

Material delivery to site

Proteção contra desprendimentos - Gore Quarry 2018

GBE-500A after rockfall

 

Comprimento do sistema

100 m

 

Ano de instalação

2018

Situação inicial

Planned extensions to the sandstone, Gritstone quarry required the extraction of overburden. Materials had the potential to travel down the outer edge of the site, down to the A44 road.

Key Geosolutions undertook rockfall analysis and calculated that a 500kJ and 3 metres high rockfall system would be required.

Descrição

Derbyshire Geotechnical contacted Geobrugg for advice on system types best suited for this location.

After an initial site visit, it was agreed that the GBE-500A would be the best option as the reduced post weight over that of the GBE-500A-R allowed for easier installation due to the limited access routes to the location.

The 100 m long system with post spacings of 10 m (11 posts) was secured with 2nr 4 m long threaded bars. Upslope and lateral anchors were 6 m long threaded bars fitted with Geobrugg flexheads.

Promotor

Tarmac Ltd

Empreteiro

Key Geosolutions

Contratante

Derbyshire Geotechnical

Outras empresas envolvidas

None

Objecto protegido

Pedreira/ Minas

Proteção contra a corrosão

GEOBRUGG SUPERCOATING

O seu contacto local

Kevin Coyle
 

Kevin Coyle

Regional Manager Northeast

Riscos naturais
Engenharia Hidráulica
Geobrugg North America, LLC,3 Beaudet Terr,CT 06237 Columbia / Estados Unidos Regional Manager Northeast

E-mail

Saleh Feidi
 

Saleh Feidi

Riscos naturais
Engenharia Hidráulica
Geobrugg North America, LLC,8921 Emperor Ave.,91775 San Gabriel, California / Estados Unidos

E-mail

John Kalejta
 

John Kalejta

Riscos naturais
Engenharia Hidráulica
Geobrugg North America, LLC,KS 67226 Wichita / Estados Unidos

E-mail

Bob Lyne
 

Bob Lyne

Riscos naturais
Engenharia Hidráulica
Geobrugg North America, LLC,8004 Windspray Drive,NC 27358 Summerfield / Estados Unidos

E-mail

Pierce Runnels, Civil Engineer
   

Pierce Runnels

General Manager Geobrugg North America

Riscos naturais
Geobrugg North America, LLC,22 Centro Algodones , Civil Engineer General Manager Geobrugg North America

E-mail

Tim Shevlin
 

Tim Shevlin

Riscos naturais
Geobrugg North America, LLC,OR 97302 Salem / Estados Unidos

E-mail