비탈면 보강 시스템 - Greenhithe 2022

View eastwards of slope stabilisation

비탈면 보강 시스템 - Greenhithe 2022

View southwards from crest of slope

 

설치 년도

2022

Situation

A sudden landslip in November 2021 was the first indication of underlying instability of the existing chalk cutting on the northern side. Immediate reactive works were needed to clear vegetation and underlying chalk material from the cess and track.

Tony Gee was engaged as the designer to engineer a permanent solution to ensure the stability of the cutting going forward. BAM Ritchies were chosen as the specialist geotechnical contractor to install the solution.

Geology

Lewes Nodular Chalk Formation, Seaford Chalk Formation And Newhaven Chalk Formation (undifferentiated) - Chalk. Sedimentary Bedrock formed approximately 72 to 94 million years ago in the Cretaceous Period. Local environment previously dominated by warm chalk seas.

Description

A solution of TECCO G45/2 mesh was chosen along with TECMAT within the upper half of the slope to provide slope stability and erosion protection. The final solution included 340 rock bolts, the lower half of which were installed from track level during a possession with the help of Pro Rail Services long-reach RRV’s.

Customer

Engineering

Contractor

Protected object

Railway

부식방지

GEOBRUGG SUPERCOATING

Your local contact

René Müller
   

René Müller

Country Manager Kantone AG BE BL BS FR GE JU NE SO VD VS

자연 재해
수리학
광산 / 터널
Geobrugg AG,Industriestrasse 21,5200 Brugg / 스위스 Country Manager Kantone AG BE BL BS FR GE JU NE SO VD VS

이메일

Olivia Sartorius
   

Olivia Sartorius

자연 재해
수리학
광산 / 터널
Geobrugg AG

이메일

Alexander Bittendorfer
   

Alexander Bittendorfer

Project Manager Inspection Services

자연 재해
Geobrugg AG,Trucks via road 14 or 13 only!, Aachstrasse 11,8590 Romanshorn / 스위스 Project Manager Inspection Services

이메일

Isacco Toffoletto
   

Isacco Toffoletto

자연 재해
수리학
광산 / 터널
Geobrugg AG Ticino,Via Brusada 5,6933 Muzzano / 스위스

이메일