Böschungsstabilisierung - Greenhithe 2022

View eastwards of slope stabilisation

Böschungsstabilisierung - Greenhithe 2022

View southwards from crest of slope

 

Installationsjahr

2022

Ausgangslage

A sudden landslip in November 2021 was the first indication of underlying instability of the existing chalk cutting on the northern side. Immediate reactive works were needed to clear vegetation and underlying chalk material from the cess and track.

Tony Gee was engaged as the designer to engineer a permanent solution to ensure the stability of the cutting going forward. BAM Ritchies were chosen as the specialist geotechnical contractor to install the solution.

Geologie

Lewes Nodular Chalk Formation, Seaford Chalk Formation And Newhaven Chalk Formation (undifferentiated) - Chalk. Sedimentary Bedrock formed approximately 72 to 94 million years ago in the Cretaceous Period. Local environment previously dominated by warm chalk seas.

Massnahme

A solution of TECCO G45/2 mesh was chosen along with TECMAT within the upper half of the slope to provide slope stability and erosion protection. The final solution included 340 rock bolts, the lower half of which were installed from track level during a possession with the help of Pro Rail Services long-reach RRV’s.

Kunde

Ausführende Firma

Geschützte Objekte

Eisenbahn

Korrosionsschutz

GEOBRUGG SUPERCOATING

Planer

Ansprechpartner

Kevin H. Coyle
 

Kevin H. Coyle

Regional Manager Northeast

Naturgefahren
Uferschutz/Wasserbau
Geobrugg North America, LLC,3 Beaudet Terr,Columbia CT 06237 / USA Regional Manager Northeast

E-Mail

Saleh Feidi
 

Saleh Feidi

Regional Manager California

Naturgefahren
Uferschutz/Wasserbau
Geobrugg North America, LLC,8921 Emperor Ave.,San Gabriel, California 91775 / USA Regional Manager California

E-Mail

John Kalejta
 

John Kalejta

Regional Manager Central US

Naturgefahren
Uferschutz/Wasserbau
Geobrugg North America, LLC,3215 67th Avenue Pl,Greeley CO 80634 / USA Regional Manager Central US

E-Mail

Bob Lyne
 

Bob Lyne

Regional Manager Southeast

Naturgefahren
Uferschutz/Wasserbau
Geobrugg North America, LLC,8004 Windspray Drive,Summerfield NC 27358 / USA Regional Manager Southeast

E-Mail

Pierce Runnels, Civil Engineer
   

Pierce Runnels

General Manager Geobrugg North America

Naturgefahren
Geobrugg North America, LLC,22 Centro Algodones,NM 87001 Algodones / USA , Civil Engineer General Manager Geobrugg North America

E-Mail

Tim Shevlin
 

Tim Shevlin

Sales Director

Naturgefahren
Geobrugg North America, LLC,Salem OR 97302 / USA Sales Director

E-Mail