Start of the reconstruction work of the damaged roadways

边坡稳定 - Yellowstone 2022

Work in progress for the slope stabilization system

边坡稳定 - Yellowstone 2022

Final touches on the TECCO Green

 

安装年份

2022

情况

In June 2022, Yellowstone National Park experienced historic flooding – damaging roads, water and wastewater systems, electrical infrastructure and other critical park infrastructure. To help with the reconstruction of the damaged roadways, GeoStabilization International was awarded two emergency design-build contracts for slope stabilization.
 

描述

The first works were done on the Old Gardiner Road Bypass at Mammoth Hot Springs, where damage at the Park’s North Entrance, cut off access to Gardiner, Montana. Approximately 20,000 square feet (1860 m2) of pinned mesh stabilized the slope, using our TECCO Green G65/3 to help promote revegetation.
 
The second included a buildout of approximately 120 linear feet (35 m) of the roadway at the East Entrance Gates adjacent to Middle Creek where flooding caused erosion of the bank and placed US Highway 14 in Wyoming at risk.

 

The pictures were provided by GeoStabilization International.

防护对象

Road, Touristic infrastructure, Infrastructure

腐蚀保护

GEOBRUGG SUPERCOATING

本地联系方式

Roger Moor
   

Roger Moor

Country Manager Ost- und Zentralschweiz, Liechtenstein

自然災害防護
Hydraulic Engineering
矿井/隧道
Geobrugg AG,Aachstrasse 11,8590 Romanshorn / 瑞士 Country Manager Ost- und Zentralschweiz, Liechtenstein

联系地址

René Müller
   

René Müller

Country Manager Kantone AG BE BL BS FR GE JU NE SO VD VS

自然災害防護
Hydraulic Engineering
矿井/隧道
Geobrugg AG,Industriestrasse 21,5200 Brugg / 瑞士 Country Manager Kantone AG BE BL BS FR GE JU NE SO VD VS

联系地址

Alexander Bittendorfer
   

Alexander Bittendorfer

Project Manager Inspection Services

自然災害防護
Geobrugg AG,Aachstrasse 11,8590 Romanshorn / 瑞士 Project Manager Inspection Services

联系地址

Isacco Toffoletto
   

Isacco Toffoletto

Ticino Country Manager

自然災害防護
Hydraulic Engineering
矿井/隧道
Geobrugg AG Ticino,Stabile Cometal, via Pizzante 7,6595 Riazzino / 瑞士 Ticino Country Manager

联系地址