Stromeferry Railway Station

边坡稳定 - Stromeferry Railway Station 2021

Railway protection with TECCO mesh

边坡稳定 - Stromeferry Railway Station 2021

TECCO on rock slope

 
 

安装年份

2021

情况

Several rock blocks had fallen into the cess, the largest of which was 1.8 x 1.0 x 0.7 cubic meters. After inspection, a length of 80 meters was found to have the potential for failure.
The designer needed a strong solution, which was quick to design and rapidly available for emergency repairs.

地質學

Lewisian Gneiss

描述

We supplied TECCO G65/3 on short notice to a remote site in the Highlands. While working with the designer in the background, we ensured they had all the necessary technical data for their design.

客户

Network Rail

承包商

Scots Rope Access

防护对象

Railway

腐蚀保护

GEOBRUGG SUPERCOATING

工程

本地联系方式

Kevin H. Coyle
 

Kevin H. Coyle

Regional Manager Northeast

自然災害防護
Hydraulic Engineering
Geobrugg North America, LLC,3 Beaudet Terr,Columbia CT 06237 / 美国 Regional Manager Northeast

联系地址

Saleh Feidi
 

Saleh Feidi

Regional Manager California

自然災害防護
Hydraulic Engineering
Geobrugg North America, LLC,8921 Emperor Ave.,San Gabriel, California 91775 / 美国 Regional Manager California

联系地址

John Kalejta
 

John Kalejta

Regional Manager Central US

自然災害防護
Hydraulic Engineering
Geobrugg North America, LLC,3215 67th Avenue Pl,Greeley CO 80634 / 美国 Regional Manager Central US

联系地址

Bob Lyne
 

Bob Lyne

Regional Manager Southeast

自然災害防護
Hydraulic Engineering
Geobrugg North America, LLC,8004 Windspray Drive,Summerfield NC 27358 / 美国 Regional Manager Southeast

联系地址

Pierce Runnels, Civil Engineer
   

Pierce Runnels

General Manager Geobrugg North America

自然災害防護
Geobrugg North America, LLC,22 Centro Algodones , Civil Engineer General Manager Geobrugg North America

联系地址

Tim Shevlin
 

Tim Shevlin

Sales Director

自然災害防護
Geobrugg North America, LLC,Salem OR 97302 / 美国 Sales Director

联系地址