Hydroelectric Power Plant Tunnel

-, 秘鲁
2014
客户
-
防护对象
Other
腐蚀保护
GEOBRUGG SUPERCOATING
稳定的地区
5000 m²
铆钉长度
2 m - 4 m
铆钉模式a
1.5 m / 1.5 m
情况

During construction of the headrace tunnel in July 2012 for a hydro power plant some severe rockburst occured. The high internal stress in the rock and overburden over 1000 m on top of the tunnel as well as the brittle metamophic character with a rock mass rating RMR › 65 caused some severe problems during the project.

描述

The tunnel was divided in sectors to analyse the stress level in regard to the high stress classification whereas it shows that some rockbursts of level 2 and 3 occured. In the most critical zone a support system with MINAX® 80/4 was applied in combination with mechanized installation thanks to Geobrugg's MESHA® handler. The installation time had been decreased between 20 to 25% and safety for workes was significantly improved.

本地联系方式

Roger Moor
Roger Moor
Country Manager Ost- und Zentralschweiz, Liechtenstein
自然災害防護, Coastal Erosion Protection, 矿井/隧道
Geobrugg AG
Aachstrasse 11
8590 Romanshorn / 瑞士
René Müller
René Müller
Country Manager Kantone AG BE BL BS FR GE JU NE SO VD VS
自然災害防護, 矿井/隧道
Geobrugg AG
Industriestrasse 21
5200 Brugg / 瑞士
Isacco Toffoletto
Isacco Toffoletto
Ticino Country Manager
自然災害防護, 矿井/隧道
Geobrugg AG Ticino
Stabile Cometal, via Pizzante 7
6595 Riazzino / 瑞士