Trek route to Shri Mata Vaishno Devi Shrine (1)

落石防护 - Trek route to Shri Mata Vaishno Devi Shrine (1) 2016

GBE-3000A rockfall barrier protecting pilgrims' route to Shri Mata Vaishno Devi Shrine

落石防护 - Trek route to Shri Mata Vaishno Devi Shrine (1) 2016

Target of all pilgrims - Holy Cave located in the folds of the three peaked mountain named Trikuta

落石防护 - Trek route to Shri Mata Vaishno Devi Shrine (1) 2016

Existing, stiff rockfall canopies were not able to withstand rockfalls existing along the trek and had to be extra protected by rockfall barriers

落石防护 - Trek route to Shri Mata Vaishno Devi Shrine (1) 2016

Density of rockfalls was quite big, here smaller ones

落石防护 - Trek route to Shri Mata Vaishno Devi Shrine (1) 2016

The area was constantly endangered by rockfalls

落石防护 - Trek route to Shri Mata Vaishno Devi Shrine (1) 2016

GBE-3000A and RXE-8000 rockfall barriers during installation - visible the route trek below, adjacent to steep rock face

落石防护 - Trek route to Shri Mata Vaishno Devi Shrine (1) 2016

Installation of the RXE-8000 rockfall barrier in progress

落石防护 - Trek route to Shri Mata Vaishno Devi Shrine (1) 2016

RXE-8000 rockfall barrier after installation protecting the trek route below from the biggest rockfalls

落石防护 - Trek route to Shri Mata Vaishno Devi Shrine (1) 2016

RXE-5000 rockfall barrier after installation protecting the trek route below

落石防护 - Trek route to Shri Mata Vaishno Devi Shrine (1) 2016

Closer look on GBE-3000A rockfall barrier after installation

落石防护 - Trek route to Shri Mata Vaishno Devi Shrine (1) 2016

GBE-3000A after installation - visible smaller rockfalls already stopped by the barrier

落石防护 - Trek route to Shri Mata Vaishno Devi Shrine (1) 2016

Some areas required extra active slope stabilization using high-tensile steel wire mesh TECCO® G65/3 and QUAROX® net

落石防护 - Trek route to Shri Mata Vaishno Devi Shrine (1) 2016

GBE-3000A rockfall barriers protecting the route trek below, adjacent to steep rock face

 

系统长度

25 m - 110 m

 

安装年份

2016

情况

There had been several cases of rockfall and landslides in the trek route of the Holy Shrine of Mata Vaishno Devi. Therefore, the Shrine Board decided to actively stabilize the 75º and higher steep slope, up to a maximum height of 70 m in this section. A protective measure had to be selected to stabilize the exposed cutting against superficial instabilities, tilting as well as sliding of individual blocks and rockfalls.

描述

The flexible slope stabilization system consists of TECCO® G65/3 high-tensile steel wire mesh and QUAROX® rolled cable net, system spike plates and soil nails has been selected. Spike plates which match the load capacity of the mesh serve to fix the mesh to soil or rock nails. By tensioning these nails, and recessing the spike plates into the ground, the mesh is adequately tensioned to ensure it follows the surface contours.

Based on the survey results, the authorities also decided to apply a rockfall protection barriers from Geobrugg. With its ring nets made of high-tensile steel wire the barrier design has been tested and approved to absorb impact energies of up to 8000 kJ. A total number of 15 barriers were installed in different locations with energy absorption capacity ranging from 3000 kJ up to 8000 kJ.

See also our slope project Trek route to Shri Mata Vaishno Devi Shrine (2)

客户

Shri Mata Vaishno Devi Shrine Board

承包商

Pioneer Foundation Engineers Pvt Ltd

防护对象

Road, Building, Touristic infrastructure, Infrastructure, Architecture, Other

腐蚀保护

Galvanized, GEOBRUGG SUPERCOATING

工程

Tehri Hydro Development Corporation Ltd

其他安装的应用程序

边坡稳定

本地联系方式

Roger Moor
   

Roger Moor

Country Manager Ost- und Zentralschweiz, Liechtenstein

自然災害防護
Hydraulic Engineering
矿井/隧道
Geobrugg AG,Aachstrasse 11,8590 Romanshorn / 瑞士 Country Manager Ost- und Zentralschweiz, Liechtenstein

联系地址

René Müller
   

René Müller

Country Manager Kantone AG BE BL BS FR GE JU NE SO VD VS

自然災害防護
Hydraulic Engineering
矿井/隧道
Geobrugg AG,Industriestrasse 21,5200 Brugg / 瑞士 Country Manager Kantone AG BE BL BS FR GE JU NE SO VD VS

联系地址

Alexander Bittendorfer
   

Alexander Bittendorfer

Project Manager Inspection Services

自然災害防護
Geobrugg AG,Aachstrasse 11,8590 Romanshorn / 瑞士 Project Manager Inspection Services

联系地址

Isacco Toffoletto
   

Isacco Toffoletto

Ticino Country Manager

自然災害防護
Hydraulic Engineering
矿井/隧道
Geobrugg AG Ticino,Stabile Cometal, via Pizzante 7,6595 Riazzino / 瑞士 Ticino Country Manager

联系地址