Estados Unidos
Estados Unidos

Cougar Corner

Rogers Pass Area, Canadá
2016
Promotor
Parks Canada Agency
Empreteiro
Alpine Solutions Avalanche Services - Brian Gould
Contratante
BAT Construction Ltd.
Objecto protegido
Estrada
Comprimento do sistema
6 m - 91 m
Altura efectiva (Dĸ, espessura de neve)
3.5, 4.5
Proteção contra a corrosão
Galvanizado, GEOBRUGG SUPERCOATING
Situação inicial

The Trans-Canada highway travels through the Glacier National Park and over Rogers Pass which is well known for numerous avalanches each year.

Since the late 1950’s avalanche control was conducted by Parks Canada Agency and the Canadian Armed Forces by shelling slide areas with howitzers. While this mitigation system functioned, there was still the issue of blocking the Trans-Canada by man-made slides. Remote Avalanche Control Systems (RACS) were also considered, however there was still a potential of blocking the highway with snow slides. To keep the highway clear all winter long it was decided to hold the snow in place with snow nets.

In December 2015, Parks Canada Agency invited contractors to bid on installing approximately 2000 meters of Dk 3.5 and Dk 4.5 snow nets. Avalanches in Glacier National Park slide directly on to the Trans-Canada Highway which runs right through the park. Closed highways cost Canada millions of dollars every year if blocked due to snow and rock slides.


Descrição

Three slide paths were to be secured. They are called Cougar Corner No. 6, 7, and 8. Each slide area has its own challenges.

Alpine Solutions determined the net locations and net sizes as well as prescribing three Geobrugg UX Debris Flow Barriers in channels too incised to accommodate traditional snow nets.

Bidding was a challenge for contractors as the site was covered with 4 meters of snow in December. BAT Construction Ltd. was the successful bidder, and chose Geobrugg SPIDER® Avalanche. The contractor was able to install over 1000 meters of nets and drill anchors for 2000 meters of nets all in the summer of 2016. No small feat at this location!

To date this is the largest snow net project in North and South America: 1000 meters done so far, 1000 meters more to go. First debris flow barrier installed entirely by helicopters in North America.

O seu contacto local

Kevin H. Coyle
Kevin H. Coyle
Regional Manager Northeast
Riscos naturais, Coastal Erosion Protection
Geobrugg North America, LLC
3 Beaudet Terr
Columbia CT 06237 / Estados Unidos
Saleh Feidi
Saleh Feidi
Regional Manager California
Riscos naturais, Coastal Erosion Protection
Geobrugg North America, LLC
8921 Emperor Ave.
San Gabriel, California 91775 / Estados Unidos
John Kalejta
John Kalejta
Regional Manager Central US
Riscos naturais, Coastal Erosion Protection
Geobrugg North America, LLC
3215 67th Avenue Pl
Greeley CO 80634 / Estados Unidos
Bob Lyne
Bob Lyne
Regional Manager Southeast
Riscos naturais, Coastal Erosion Protection
Geobrugg North America, LLC
8004 Windspray Drive
Summerfield NC 27358 / Estados Unidos
Pierce Runnels, Civil Engineer
Pierce Runnels, Civil Engineer
General Manager Geobrugg North America
Riscos naturais
Geobrugg North America, LLC
22 Centro Algodones
Telefone +1 505 771 4080
Telemóvel +1 505 400 0796

E-mail

Tim Shevlin
Tim Shevlin
Sales Director
Riscos naturais
Geobrugg North America, LLC
Salem OR 97302 / Estados Unidos