Palena - Abruzzo, Włoch
2003
Inwestor
Municipality of Palena
Projektant
Dr. Ing. Alessandro Marini
Wykonawca
CO.GE.PRI. srl - PIaneta Montagna
Chroniony Objekt
Road, Building
Wystawy
North
Sytuacja początkowa

The stretch of embankment in question was long since subject to erosion problems because of the presence of nonlinear stretches in correspondence with the material removal, in case of signifi cant fl ows. This involved problems of poor stability for the road above and for the buildings that were immediately behind.

Opis zastosowanego rozwiazania

The TECCO® choice by the design engineer was made for various reasons of which we should mention the high-tensile steel wire TECCO® mesh unit (high tensile 1770 N/mm2); the special anticorrosive treatment with aluminium-zinc alloy (GEOBRUGG SUPERCOATING); and the high bearing resistance of the mesh, by applying tension to it with the penetration of the special TECCO® cuspate shaped plates for the distribution of the anchorage loads in the bank's soil. These elements guaranteed by the TECCO® System are not present in the traditional bank protection method with gabions. Furthermore, the
particularly fast timeline for the implementation of the TECCO® System played a major part given that the work was done late in the season.

Osoba kontaktowa na miejscu

Roger Moor
Roger Moor
Country Manager Ost- und Zentralschweiz, Liechtenstein
Zagrożeniami naturalnymi, Coastal Erosion Protection, Kopalnie / Wydobycie / Tunel
Geobrugg AG
Aachstrasse 11
8590 Romanshorn / Szwajcaria
René Müller
René Müller
Country Manager Kantone AG BE BL BS FR GE JU NE SO VD VS
Zagrożeniami naturalnymi, Kopalnie / Wydobycie / Tunel
Geobrugg AG
Industriestrasse 21
5200 Brugg / Szwajcaria
Isacco Toffoletto
Isacco Toffoletto
Ticino Country Manager
Zagrożeniami naturalnymi, Kopalnie / Wydobycie / Tunel
Geobrugg AG Ticino
Stabile Cometal, via Pizzante 7
6595 Riazzino / Szwajcaria