Szwajcaria
Szwajcaria

myGeobrugg

Ochrona przed spływami gruzowymi (rumowisko) i płytkimi  osuwiskami - Kaikōura SR11 2023

SR11 shallow landslide barrier in December 2023

Ochrona przed spływami gruzowymi (rumowisko) i płytkimi  osuwiskami - Kaikōura SR11 2023

SR11 SL-150 at completion November 2017

Ochrona przed spływami gruzowymi (rumowisko) i płytkimi  osuwiskami - Kaikōura SR11 2023

SR11 looking upslope after March 2023 landslide

Ochrona przed spływami gruzowymi (rumowisko) i płytkimi  osuwiskami - Kaikōura SR11 2023

SR11 from above: Note no impact on road and large 10 m³ boulder

Ochrona przed spływami gruzowymi (rumowisko) i płytkimi  osuwiskami - Kaikōura SR11 2023

SR11 Looking South after 2023 landslide

Ochrona przed spływami gruzowymi (rumowisko) i płytkimi  osuwiskami - Kaikōura SR11 2023

SR11 Looking North after 2023 landslide

Ochrona przed spływami gruzowymi (rumowisko) i płytkimi  osuwiskami - Kaikōura SR11 2023

Looking North - Screenshots from scaling video showing 1 m³ rock impacting filled barrier

Ochrona przed spływami gruzowymi (rumowisko) i płytkimi  osuwiskami - Kaikōura SR11 2023

SL-150 barrier after clearing and maintenance

Ochrona przed spływami gruzowymi (rumowisko) i płytkimi  osuwiskami - Kaikōura SR11 2023

SR11 Looking North SH1 – 2023 post clearing

 

Zastosowane systemy

 

Rok Instalacji / Montazu

2023

Sytuacja początkowa

The 2016 Kaikōura M7.8 Earthquake caused widespread damage to the road and rail corridor some 20km North and South of the Kaikōura town ship. Over 40 major slips inundated the road and rail with over 750,000 m³ of material from source zones up to 500 m above sea level. The highly fractured Greywacke meant future landslides were expected, creating a requirement to install shallow landslide barriers in several SH1 and Rail locations. To date (2023), six SL150 barriers have been installed along the corridor. The SL150 barrier at the SR11 site required steeper upslope anchors to avoid interaction with the rail tunnel and also a rockface connection at Northern end. The barrier is 3.5 m high and 48 m long (6 x 8 m fields).

In March 2023, heavy rainfall triggered a large 600 m³ landslide at the SR11 site. Since the SL150 barrier installation (2017), only smaller 300 – 400 mm rocks had released and impacted the system. The landslide was comprised of a mixture of soil, gravels, vegetation and large blocks. The largest block was › 10 m³ and came to rest against the fourth post (South-North). The barrier was filled to approximately 0.5 m from the top in the centre two fields and had 1.25 - 1.5 m elongation, just touching the roadside barrier. Overall, the barrier performed exceptionally well.

Opis zastosowanego rozwiazania

The initial response was to spread some of the debris behind the barrier to create extra catchment capacity and prevent overtopping in the event of the head scarp regressing further. Rock Control were then mobilised to clear and reinstate the barrier, which took five shifts.

First, a top-down scaling campaign was conducted, realising further blocks into the filled barrier. The largest block was approximately 1 m³, which was successfully stopped by the barrier. An excavator from roadside then removed 600 m³ of debris, with a rock breaker required for the largest block prior to removal. Rock Control then carried out maintenance on the barrier, which required one post, two upslope brake rings and two mesh panels. The SL150 barrier is now back and ready for action.

Wykonawca

SRG Install - Rock Control Maintenance

Chroniony Objekt

Road

Ochrona przeciwerozyjna

GEOBRUGG SUPERCOATING

Projektant

North Canterbury Transport Infrastructure Rebuild (NCTIR) Alliance

Osoba kontaktowa na miejscu

Roger Moor
   

Roger Moor

Country Manager Ost- und Zentralschweiz, Liechtenstein

Zagrożeniami naturalnymi
Nżynieria hydrauliczna
Kopalnie / Wydobycie / Tunel
Geobrugg AG,Aachstrasse 11,8590 Romanshorn / Szwajcaria Country Manager Ost- und Zentralschweiz, Liechtenstein

Formularz kontaktowy

René Müller
   

René Müller

Country Manager Kantone AG BE BL BS FR GE JU NE SO VD VS

Zagrożeniami naturalnymi
Nżynieria hydrauliczna
Kopalnie / Wydobycie / Tunel
Geobrugg AG,Industriestrasse 21,5200 Brugg / Szwajcaria Country Manager Kantone AG BE BL BS FR GE JU NE SO VD VS

Formularz kontaktowy

Alexander Bittendorfer
   

Alexander Bittendorfer

Project Manager Inspection Services

Zagrożeniami naturalnymi
Geobrugg AG,Aachstrasse 11,8590 Romanshorn / Szwajcaria Project Manager Inspection Services

Formularz kontaktowy

Isacco Toffoletto
   

Isacco Toffoletto

Ticino Country Manager

Zagrożeniami naturalnymi
Nżynieria hydrauliczna
Kopalnie / Wydobycie / Tunel
Geobrugg AG Ticino,Stabile Cometal, via Pizzante 7,6595 Riazzino / Szwajcaria Ticino Country Manager

Formularz kontaktowy