 - A1 Highway Pyrzowice-Piekary Śląskie 2011

Deep cut along the A1 Highway between Pyrzowice and Piekary Śląskie - nailing and flexible facing using TECCO® SYSTEM³ ensure safety and a natural look

 - A1 Highway Pyrzowice-Piekary Śląskie 2011

For the cuts along the highway the top down method with benching was applied. The benches were subsequently nailed and covered with TECCO® SYSTEM³

 - A1 Highway Pyrzowice-Piekary Śląskie 2011

To make the nailing as efficient as possible, some subcontractors used drill rigs installed on an excavator. This allowed drilling works flexibility

 - A1 Highway Pyrzowice-Piekary Śląskie 2011

November 2010 - visible installation of self drilling TITAN nails

 - A1 Highway Pyrzowice-Piekary Śląskie 2011

To allow optimal TECCO® SYSTEM³ pre-tensioning, nails were cut to the slope face and dells around were prepared

 - A1 Highway Pyrzowice-Piekary Śląskie 2011

Flexible facing using TECCO® SYSTEM³ during installation, after the anti-erosion mats have been placed on the slope

 - A1 Highway Pyrzowice-Piekary Śląskie 2011

TECCO® SYSTEM³ partially installed - the pre-tensioning minimises the risk of further slope deformations

 - A1 Highway Pyrzowice-Piekary Śląskie 2011

Directly after nailing slope facing application, an extra layer of humus was applied to support further greening

 - A1 Highway Pyrzowice-Piekary Śląskie 2011

Thanks to the applied solutions, the greening came very fast and required only seeding

 - A1 Highway Pyrzowice-Piekary Śląskie 2011

Closer look on the fully stabilized slopes - TECCO® SYSTEM³ is nearly invisible and allows fast greening

 - A1 Highway Pyrzowice-Piekary Śląskie 2011

The highway after the opening

 - A1 Highway Pyrzowice-Piekary Śląskie 2011

Stabilized cut - thanks to the applied solutions, the slopes maintain their natural look

 

システム

 

設置年

2011

状況

The Polish A1 highway connecting Poland from south to north leads through Silesia. Because of the morphology of the terrain, deep cuts were required. Due to geological conditions and also due to the fact that this area is strongly influenced by the hard coal mining activity, slope stabilization was a must.

地質

Marls, silts, sandstones and limestones.

説明

For the following reasons designers together with the Polish National Roads selected TECCO® System as a stabilizing solution:

  •  complicated ground conditions – about 12 geotechnical layers were described, only 4 of these were rocks and all others soil in different compositions
  • there was an apprehension that after digging and taking off such mass of material, there will be a release of the energy and consequently, the slopes will be prone to collapse - which is quite common especially for such high slopes
  • the system can be designed and dimensioned against superficial instabilities which offer the possibility to arrange the nails in a more economical way due to the capability of TECCO® System  mesh in absorbing and transferring high loads
  • when slopes stabilized with TECCO® System are combined with anti-erosion mats, they can regain a natural or vegetated appearance, which is aesthetically preferred.


TECCO® System was designed to protect local instabilities of soil and rock masses. This worked perfectly, as first visible small movements occurred which were stopped by the TECCO® System mesh shortly after installation.

顧客名

General Directorate of National Roads and Motorways

落札者

BUDIMEX S.A.

保護対象

道路

腐食防止

ジェオブルッグ スーパーコーティング

エンジニアリング

Complex Project Sp. z o.o. / Transprojekt Kraków Sp. z o.o.

下請

Stump-Hydrobudowa Sp. z o.o. / Italcementaciones S.L.U. / PPI Chrobok S.A. / ZRI Chrobok sp.j.

担当者の連絡先

Roger Moor
   

Roger Moor

Country Manager Ost- und Zentralschweiz, Liechtenstein

自然災害防護
Hydraulic Engineering
鉱山/トンネル
Geobrugg AG,Aachstrasse 11,8590 Romanshorn / スイス Country Manager Ost- und Zentralschweiz, Liechtenstein

お問い合わせフォーム

René Müller
   

René Müller

Country Manager Kantone AG BE BL BS FR GE JU NE SO VD VS

自然災害防護
Hydraulic Engineering
鉱山/トンネル
Geobrugg AG,Industriestrasse 21,5200 Brugg / スイス Country Manager Kantone AG BE BL BS FR GE JU NE SO VD VS

お問い合わせフォーム

Alexander Bittendorfer
   

Alexander Bittendorfer

Project Manager Inspection Services

自然災害防護
Geobrugg AG,Aachstrasse 11,8590 Romanshorn / スイス Project Manager Inspection Services

お問い合わせフォーム

Isacco Toffoletto
   

Isacco Toffoletto

Ticino Country Manager

自然災害防護
Hydraulic Engineering
鉱山/トンネル
Geobrugg AG Ticino,Stabile Cometal, via Pizzante 7,6595 Riazzino / スイス Ticino Country Manager

お問い合わせフォーム