Protezione contro frane e colate detritiche - Bulli Pass (2) 2017

A 1,1 km long Shallow Landslide Barrier and seven Debris Flow Barriers are protecting the road at Bulli Pass in New South Wales.

Protezione contro frane e colate detritiche - Bulli Pass (2) 2017

Debris flow and shallow landslide barrier protecting Bulli Pass

 

Anno di installazione

2017

Situazione iniziale

The Wollongong Escarpment Area in Wollongong New South Wales is unstable and Bulli Pass is subject to rockslides especially in times of heavy rainfall. Bulli Pass has a history of slip and rock fall events. A major slip in 2008 required slope stabilisation works with the road being closed for seven weeks. Following several events, including a serious rock fall that landed on a vehicle in 2015, there have been extensive investigations into the upslope section of Bulli Pass.  After detailed analysis Geobrugg Australia was chosen as the preferred supplier of a Rock Fall and Landslide mitigation system.

Descrizione

The project reduces the residual slope risk profile from landslide and rock fall events. The project consisted of a 1.1 km of SL-150 Shallow Landslide Barrier and a combination of VX and UX flood debris catchment nets.  The system now provides rock fall and landslide protection from a road that has 14'000 car movements a day.  The barrier is 3.5 m high including over 1'000 rock nail anchors constructed in difficult terrain. The Barrier is also capable of containing a 500 kg rock travelling at 160 km/hour.

More information:

- Roads & Maritime, New South Wales

Cliente

Roads and Maritime Authority, New South Wales

Contraente:

Specialised Geo Pty Ltd (GHD Contractor)

Oggetto protetto

Strada

Protezione dalla corrosione

GEOBRUGG ULTRACOATING

Progettazione:

Department of Public Works, (Project Management)

Altre società partecipanti

Consultant Andrew Hunter Coffey/GHD (Geotechnical Consultant); Consultant Philip Flentje (University of Wollongong)

Altre applicazioni installate

Protezione da caduta massi

Il contatto locale

Kevin H. Coyle
 

Kevin H. Coyle

Regional Manager Northeast

Sistemi contro il dissesto idrogeologico
Ingegneria idraulica
Geobrugg North America, LLC,3 Beaudet Terr,Columbia CT 06237 / Stati Uniti Regional Manager Northeast

E-mail

Saleh Feidi
 

Saleh Feidi

Regional Manager California

Sistemi contro il dissesto idrogeologico
Ingegneria idraulica
Geobrugg North America, LLC,8921 Emperor Ave.,San Gabriel, California 91775 / Stati Uniti Regional Manager California

E-mail

John Kalejta
 

John Kalejta

Regional Manager Central US

Sistemi contro il dissesto idrogeologico
Ingegneria idraulica
Geobrugg North America, LLC,3215 67th Avenue Pl,Greeley CO 80634 / Stati Uniti Regional Manager Central US

E-mail

Bob Lyne
 

Bob Lyne

Regional Manager Southeast

Sistemi contro il dissesto idrogeologico
Ingegneria idraulica
Geobrugg North America, LLC,8004 Windspray Drive,Summerfield NC 27358 / Stati Uniti Regional Manager Southeast

E-mail

Pierce Runnels, Civil Engineer
   

Pierce Runnels

General Manager Geobrugg North America

Sistemi contro il dissesto idrogeologico
Geobrugg North America, LLC,22 Centro Algodones , Civil Engineer General Manager Geobrugg North America

E-mail

Tim Shevlin
 

Tim Shevlin

Sales Director

Sistemi contro il dissesto idrogeologico
Geobrugg North America, LLC,Salem OR 97302 / Stati Uniti Sales Director

E-mail