Protection contre les chutes de pierres - Trbovlje rockslide protection 2016

Overview of the situation after the event.

Protection contre les chutes de pierres - Trbovlje rockslide protection 2016

Overview of the situation after the event.

Protection contre les chutes de pierres - Trbovlje rockslide protection 2016

Slope preparation for the installation works. Cleaning of the surface.

Protection contre les chutes de pierres - Trbovlje rockslide protection 2016

Example of conditions on the installation site, where helicopter transport was involved.

Protection contre les chutes de pierres - Trbovlje rockslide protection 2016

Example of conditions on the installation site, where helicopter transport was involved.

Protection contre les chutes de pierres - Trbovlje rockslide protection 2016

Border post positions - highest helicopter pilot accuracy is clearly visible!

Protection contre les chutes de pierres - Trbovlje rockslide protection 2016

Final posts adjustments, line of protection already visible.

Protection contre les chutes de pierres - Trbovlje rockslide protection 2016

Transmission ropes installation. Visible tremendous size of the barrier and it's post profiles.

Protection contre les chutes de pierres - Trbovlje rockslide protection 2016

ROCCO® ring-net bundles prepared for "curtain" installation.

Protection contre les chutes de pierres - Trbovlje rockslide protection 2016

ROCCO® ring-net installation.

Protection contre les chutes de pierres - Trbovlje rockslide protection 2016

RXE-8000 barrier fully installed.

Protection contre les chutes de pierres - Trbovlje rockslide protection 2016

RXE-8000 barrier fully installed.

Protection contre les chutes de pierres - Trbovlje rockslide protection 2016

RXE-8000 barrier fully installed. Perfect perspective concerning protected area.

Protection contre les chutes de pierres - Trbovlje rockslide protection 2016

Additional line of protection: GBE-500A barrier.

Protection contre les chutes de pierres - Trbovlje rockslide protection 2016

RXE-8000 ready to protect. Size of the whole rock slide damage also visible.

Protection contre les chutes de pierres - Trbovlje rockslide protection 2016

Whole project overview - desctruction aread clearly visible.

 

Longueur du système

- 40 m

 

Année d’installation

2016

Situation de départ

On 20th February 2016 over 500 cubic meters of rock and debris collapsed onto the district road between the county seat Trbovlje and Ljubljana. Not only was the important road blocked, the residents were also cut off from electricity and water.

The debris removal on route R1-223 had to be completed in the shortest possible time, but first sustainable protection measures needed to be developed and installed. Site investigations and software analysis conducted by geologists and engineers indicate a significant hazard potential. The heavily fractured residual rock mass at the mountain top cannot be taken down as it could damage an important nearby railway. However, parallel to the site investigation and software analysis, limited rock scaling was also being performed.

Description

Construction commenced on March 8th with rock drilling to install anchors and base plates for the barrier’s post foundations. Based on the study results national authorities decided to apply a Geobrugg rockfall protection system from the RXE-Series. With its ring nets made of high-tensile steel wire the barrier design has been tested and approved to absorb impact energies of up to 8,000 [kJ]. Additionally, two GBE-500A systems were selected to protect the lower part of the slope.

The posts, ringnet’s ropes and accessories produced and pre-assembled in Romanshorn, Switzerland, were already delivered to Trbovlje by mid-March. The biggest helicopter of the Slovenian Armed Forces delivered the four preassembled ring net bundles along with the five posts, weighing almost 2 metric tons, to the heavily inaccessible terrain. Despite high winds the helicopter crew made the decision: “We’re flying!” The experience of the entire ground and helicopter crew was needed to connect the posts to the base plates within a millimeter of accuracy. The mega-barrier technical acceptance inspection took place on April 4th, the same day officials, stakeholders and the public are welcomed to the inaugural reopening of the newly repaired and secured road.

Client

Slovenian Infrastructure Agency (DRSI)

Entrepreneur

Kaskader

Objet protégé

Route/Rue

Protection anticorrosion

galvanisé, GEOBRUGG SUPERCOATING

Ingénierie

EHO Projekt

Votre contact local

Roger Moor
   

Roger Moor

Country Manager Ost- und Zentralschweiz, Liechtenstein

Risques naturels
Ingénierie Hydraulique
Exploitation minière / Tunnel
Geobrugg AG,Aachstrasse 11,8590 Romanshorn / Suisse Country Manager Ost- und Zentralschweiz, Liechtenstein

E-mail

René Müller
   

René Müller

Country Manager Cantons AG BE BL BS FR GE JU NE SO VD VS

Risques naturels
Ingénierie Hydraulique
Exploitation minière / Tunnel
Geobrugg AG,Industriestrasse 21,5200 Brugg / Suisse Country Manager Cantons AG BE BL BS FR GE JU NE SO VD VS

E-mail

Alexander Bittendorfer
   

Alexander Bittendorfer

Project Manager Inspection Services

Risques naturels
Geobrugg AG,Aachstrasse 11,8590 Romanshorn / Suisse Project Manager Inspection Services

E-mail

Isacco Toffoletto
   

Isacco Toffoletto

Ticino Country Manager

Risques naturels
Ingénierie Hydraulique
Exploitation minière / Tunnel
Geobrugg AG Ticino,Stabile Cometal, via Pizzante 7,6595 Riazzino / Suisse Ticino Country Manager

E-mail