Suíça
Suíça

myGeobrugg

Estabilização de taludes - Greenhithe 2022

View eastwards of slope stabilisation

Estabilização de taludes - Greenhithe 2022

View southwards from crest of slope

 

Ano de instalação

2022

Situação inicial

A sudden landslip in November 2021 was the first indication of underlying instability of the existing chalk cutting on the northern side. Immediate reactive works were needed to clear vegetation and underlying chalk material from the cess and track.

Tony Gee was engaged as the designer to engineer a permanent solution to ensure the stability of the cutting going forward. BAM Ritchies were chosen as the specialist geotechnical contractor to install the solution.

Geologia

Lewes Nodular Chalk Formation, Seaford Chalk Formation And Newhaven Chalk Formation (undifferentiated) - Chalk. Sedimentary Bedrock formed approximately 72 to 94 million years ago in the Cretaceous Period. Local environment previously dominated by warm chalk seas.

Descrição

A solution of TECCO G45/2 mesh was chosen along with TECMAT within the upper half of the slope to provide slope stability and erosion protection. The final solution included 340 rock bolts, the lower half of which were installed from track level during a possession with the help of Pro Rail Services long-reach RRV’s.

País / Região

Reino Unido

Promotor

Empreteiro

Contratante

Objecto protegido

Caminho de ferro

Proteção contra a corrosão

GEOBRUGG SUPERCOATING

O seu contacto local

René Müller
   

René Müller

Country Manager Western Switzerland

Riscos naturais
Engenharia Hidráulica
Mineração / Túneis
Geobrugg AG,Industriestrasse 21,5200 Brugg / Suíça Country Manager Western Switzerland

E-mail

Olivia Sartorius
   

Olivia Sartorius

Project Manager Sales Eastern Switzerland

Riscos naturais
Engenharia Hidráulica
Mineração / Túneis
Geobrugg AG Project Manager Sales Eastern Switzerland

E-mail

Alexander Bittendorfer
   

Alexander Bittendorfer

Project Manager Inspection Services

Riscos naturais
Monitoring
Geobrugg AG,Trucks via road 14 or 13 only!, Aachstrasse 11,8590 Romanshorn / Suíça Project Manager Inspection Services

E-mail

Isacco Toffoletto
   

Isacco Toffoletto

Country Manager Southern Switzerland

Riscos naturais
Engenharia Hidráulica
Mineração / Túneis
Geobrugg AG Ticino,Via Brusada 5,6933 Muzzano / Suíça Country Manager Southern Switzerland

E-mail