Natural Gas Pipeline Project Central Tennessee

Укрепление склонов - Natural Gas Pipeline Project Central Tennessee 2014

Completed slope stabilization, revegetating and eco-friendly - with deer traversing the slope

Укрепление склонов - Natural Gas Pipeline Project Central Tennessee 2014

Clearing the slope. Photo thanks to courtesy of Geofirma, LLC

Укрепление склонов - Natural Gas Pipeline Project Central Tennessee 2014

Excavating the trench for the pipeline. Photo thanks to courtesy of Geofirma, LLC

Укрепление склонов - Natural Gas Pipeline Project Central Tennessee 2014

Drilling and installation of high tensile steel TECCO® SYSTEM³ after the pipeline was covered. Photo thanks to courtesy of Geofirma, LLC

Укрепление склонов - Natural Gas Pipeline Project Central Tennessee 2014

Lightweight modular drilling machine used for top-down installation of soil nails. Photo thanks to courtesy of Geofirma, LLC

Укрепление склонов - Natural Gas Pipeline Project Central Tennessee 2014

TECCO® SYSTEM³ during installation - visible dells around the nails for system pretensioning

 

Год установки

2014

Ситуация

Natural Gas pipeline installed involving clearing of slopes and covering a 20 in transmission line. The two slopes detailed on this project needed stabilizing to protect the integrity of the transmission line, personal property and the public from a slope failure. The solution required a cost effective system that could meet site challenges and provide safe, eco friendly slopes.

The nailed (anchored) TECCO® System effectively stabilized the slopes protecting the integrity of the natural gas pipeline, property and the public. The revegetated slope looks great and is eco-friendly. Grooming of the slope is not a problem and animals can easily traverse the mitigated area.

Rеология

Residual soil/coluvium

Описание

The solution was 82 000 ft² of anchored TECCO® System utilizing TECCO® G65/3 and P33/40 spike plates. Challenges for design and implementation included access to the top of the slope. This was accomplished using a light weight, modular wagon drill for the top down TECCO® installation. The pipeline had to be considered during design with anchors strategically placed around the pipeline. Cathodic protection was ensured with properly grouted anchors and installing sleeves through the TECCO® mesh for wiring.  

Клиент

Energy Company

Подрядчик

General Contractor: Sheehan Pipe Line Construction Co.

Защищаемый объект

Дорога, Жилой район, Инфраструктура, Другое

Защита от коррозии

GEOBRUGG SUPERCOATING

Проектировщик

Civil: Fisher & Arnold Inc. / Geotechnical: TTL Inc. / Design & Build Slope Stabilization Engineer: Teasley Services Group LLC

Dahil olan diğer şirketler

Geotechnical Stabilization Contractor: Geofirma LLC

Представитель в Вашем регионе

Roger Moor
   

Roger Moor

Country Manager Ost- und Zentralschweiz, Liechtenstein

Инженерная защита
Гидротехника
Горнодобывающая промышленность / Туннели
Геобругг АГ,Аахштрассе 11,8590 Романсхорн / Швейцария Country Manager Ost- und Zentralschweiz, Liechtenstein

Электронная почта

René Müller
   

René Müller

Country Manager Kantone AG BE BL BS FR GE JU NE SO VD VS

Инженерная защита
Гидротехника
Горнодобывающая промышленность / Туннели
Геобругг АГ,Industriestrasse 21,5200 Brugg / Швейцария Country Manager Kantone AG BE BL BS FR GE JU NE SO VD VS

Электронная почта

Alexander Bittendorfer
   

Alexander Bittendorfer

Project Manager Inspection Services

Инженерная защита
Геобругг АГ,Аахштрассе 11,8590 Романсхорн / Швейцария Project Manager Inspection Services

Электронная почта

Isacco Toffoletto
   

Isacco Toffoletto

Ticino Country Manager

Инженерная защита
Гидротехника
Горнодобывающая промышленность / Туннели
Geobrugg AG Ticino,Stabile Cometal, via Pizzante 7,6595 Riazzino / Швейцария Ticino Country Manager

Электронная почта