Consolidamento di versanti - Northchurch 2023

View westwards towards the tunnel portal

Consolidamento di versanti - Northchurch 2023

View of final installation

Consolidamento di versanti - Northchurch 2023

View from rope access

 
 

Anno di installazione

2023

Situazione iniziale

Slopes above a railway tunnel portal in Northchurch, Berkhamsted, had shown signs of instability. As part of the West Coast Main Line, this railway is a critical piece of infrastructure for both passengers and freight trains alike.

Tony Gee & Partners Consulting Engineers acted as the designers for the remediation of the ongoing slope instability, whilst BAM Ritchies were the contractors appointed to install the final solution.

Geologia

Holywell Nodular Chalk Formation and New Pit Chalk Formation

Descrizione

The chosen design involved a rock-bolted solution of R-32 hollow bar between 8 - 10 meters long with over 730 rock bolts used across the site, which spanned from above the tunnel portal around to the northern side of the cutting and then eastwards.

TECCO G45/2 was chosen as the right facing to stabilize the superficial instability.
BAM Ritchies used rope access techniques to install erosion control matting first, followed by TECCO G45/2.

Geobrugg worked with Tony Gee & BAM Ritchies to ensure design and installation of the TECCO system was appropriate and simple.

Cliente

Contraente:

Oggetto protetto

Ferrovia, Zona residenziale

Protezione dalla corrosione

GEOBRUGG SUPERCOATING

Progettazione:

Il contatto locale

Kevin H. Coyle
 

Kevin H. Coyle

Regional Manager Northeast

Sistemi contro il dissesto idrogeologico
Ingegneria idraulica
Geobrugg North America, LLC,3 Beaudet Terr,Columbia CT 06237 / Stati Uniti Regional Manager Northeast

E-mail

Saleh Feidi
 

Saleh Feidi

Regional Manager California

Sistemi contro il dissesto idrogeologico
Ingegneria idraulica
Geobrugg North America, LLC,8921 Emperor Ave.,San Gabriel, California 91775 / Stati Uniti Regional Manager California

E-mail

John Kalejta
 

John Kalejta

Regional Manager Central US

Sistemi contro il dissesto idrogeologico
Ingegneria idraulica
Geobrugg North America, LLC,3215 67th Avenue Pl,Greeley CO 80634 / Stati Uniti Regional Manager Central US

E-mail

Bob Lyne
 

Bob Lyne

Regional Manager Southeast

Sistemi contro il dissesto idrogeologico
Ingegneria idraulica
Geobrugg North America, LLC,8004 Windspray Drive,Summerfield NC 27358 / Stati Uniti Regional Manager Southeast

E-mail

Pierce Runnels, Civil Engineer
   

Pierce Runnels

General Manager Geobrugg North America

Sistemi contro il dissesto idrogeologico
Geobrugg North America, LLC,22 Centro Algodones , Civil Engineer General Manager Geobrugg North America

E-mail

Tim Shevlin
 

Tim Shevlin

Sales Director

Sistemi contro il dissesto idrogeologico
Geobrugg North America, LLC,Salem OR 97302 / Stati Uniti Sales Director

E-mail