Pit Lane & T12 Circuit de Spa

赛道 - Pit Lane & T12 Circuit de Spa 2020

Overlap of existing fence with a mobile debris fence (mDF350-2), tire packs installed

赛道 - Pit Lane & T12 Circuit de Spa 2020

System overview, five sections of the protective mesh system, tire packs installed

赛道 - Pit Lane & T12 Circuit de Spa 2020

Back of the system, overlap of existing fence with a mobile debris fence (mDF350-2)

赛道 - Pit Lane & T12 Circuit de Spa 2020

Pit lane extension, NORDBETON double sided barriers

 

系统长度

- 176 m

 

安装年份

2020

情况

A two months before the FIA inspection for Grade 1 status, the F1 circuit at Spa-Francorchamps was given several tasks to complete. First, was to redirect the guardrail at T12, which meant the catch fence had to be modified. Secondly, the second pitlane entrance had to be extended in order to reduce speeds near the access for emergency vehicles. Also, the track has been fully booked for the racing season, meaning all work had to be completed at night.

描述

T12: The existing permanent fence was removed, and a mobile debris fence, 3.5 meters high, was installed. Five sections have been placed in the area, adding three to the existing two.

Pit Lane: Much like the pit lane exit in Zandvoort, we used double sided NORDBETON concrete barriers. A total of 44 elements were placed in two nights. 

分包商

其他安装的应用程序

赛道

本地联系方式

Marty Hunt
   

Marty Hunt

Project Manager Motorsport Solutions

Motorsport
Geobrugg Partner - Motorsport Logistics & Technology L.L.C.,PO Box 138,IN 46167 USA Pittsboro / 美国 Project Manager Motorsport Solutions

联系地址