Milibach Torrent, Hasliberg, Canton of Bern

泥石流和滑坡防护 - Milibach Torrent, Hasliberg, Canton of Bern 2011

Filled barrier after the impact - view from downstream

泥石流和滑坡防护 - Milibach Torrent, Hasliberg, Canton of Bern 2011

Satellite image of the storm that moved across the northern Swiss Alps on October 10 (source: SF Meteo website)

泥石流和滑坡防护 - Milibach Torrent, Hasliberg, Canton of Bern 2011

Filled barrier after the impact

泥石流和滑坡防护 - Milibach Torrent, Hasliberg, Canton of Bern 2011

Filled barrier after the impact

泥石流和滑坡防护 - Milibach Torrent, Hasliberg, Canton of Bern 2011

Partially engaged UX-barrier - ready for more

泥石流和滑坡防护 - Milibach Torrent, Hasliberg, Canton of Bern 2011

Event mapping

泥石流和滑坡防护 - Milibach Torrent, Hasliberg, Canton of Bern 2011

Erosion and slope instability

泥石流和滑坡防护 - Milibach Torrent, Hasliberg, Canton of Bern 2011

Staking

泥石流和滑坡防护 - Milibach Torrent, Hasliberg, Canton of Bern 2011

Drilling with a specially equipped excavator

泥石流和滑坡防护 - Milibach Torrent, Hasliberg, Canton of Bern 2011

Installing flexheads

泥石流和滑坡防护 - Milibach Torrent, Hasliberg, Canton of Bern 2011

Foundation with installed flexheads

泥石流和滑坡防护 - Milibach Torrent, Hasliberg, Canton of Bern 2011

Ring net ready to be placed

泥石流和滑坡防护 - Milibach Torrent, Hasliberg, Canton of Bern 2011

Connecting the ring net to the ropes

泥石流和滑坡防护 - Milibach Torrent, Hasliberg, Canton of Bern 2011

Final assembly of the components

泥石流和滑坡防护 - Milibach Torrent, Hasliberg, Canton of Bern 2011

Anchor test

 

系统

 

系统长度

500 m - 7 m

 

安装年份

2011

情况

In August 2005, a storm in the Weiler Reuti and in Meiringen had caused serious debris coverage and severe damage. To protect the two settlements, a cascade comprised of 13 flexible debris flow barriers was installed to retain a cumulative volume of up to 10,000 m³ was installed.

On October 10, 2011, heavy rainfall triggered a shallow landslide containing a total of 2,000 m³ of schist in the drainage area of the Milibach river. Approximately 80 mm of rain had fallen onto a 70 cm layer of existing snow in 12 hours. The Swiss Federal Office for Environment (FOEN) categorized these heavy rainfalls as the 100-year event.

描述

This multilevel debris flow barrier system successfully retained an estimate 2,000 m³ of debris from the October 2011 100-year event before the slide had any opportunity to gain momentum and cause significant damage, as had happened in 2005. The event filled barrier no. 2 completely and barrier no. 5 partially. Barrier 1, which was situated above where the shallow landslide was triggered, remained unaffected, while barriers 3 and 4 were not filled as they have a higher basal opening.

Stopping the 2,000 m³ of debris helped prevent further erosion along the unstable banks of the Milibach River and dissipated an event that could have caused damage to the settlements further downstream. After an in-depth investigation during an on-site inspection, the customer decided to leave barrier no. 2 filled to protect the riverbanks. The debris held by barrier no. 5 is also being left and should be carried away over time as the water drains naturally.

客户

.

腐蚀保护

GEOBRUGG SUPERCOATING

其他安装的应用程序

泥石流和滑坡防护

本地联系方式

Roger Moor
   

Roger Moor

Country Manager Ost- und Zentralschweiz, Liechtenstein

自然災害防護
Hydraulic Engineering
矿井/隧道
Geobrugg AG,Aachstrasse 11,8590 Romanshorn / 瑞士 Country Manager Ost- und Zentralschweiz, Liechtenstein

联系地址

René Müller
   

René Müller

Country Manager Kantone AG BE BL BS FR GE JU NE SO VD VS

自然災害防護
Hydraulic Engineering
矿井/隧道
Geobrugg AG,Industriestrasse 21,5200 Brugg / 瑞士 Country Manager Kantone AG BE BL BS FR GE JU NE SO VD VS

联系地址

Alexander Bittendorfer
   

Alexander Bittendorfer

Project Manager Inspection Services

自然災害防護
Geobrugg AG,Aachstrasse 11,8590 Romanshorn / 瑞士 Project Manager Inspection Services

联系地址

Isacco Toffoletto
   

Isacco Toffoletto

Ticino Country Manager

自然災害防護
Hydraulic Engineering
矿井/隧道
Geobrugg AG Ticino,Stabile Cometal, via Pizzante 7,6595 Riazzino / 瑞士 Ticino Country Manager

联系地址