Lovers Walk, Brighton

Stanford Road, BN1 5PR, Brighton, 英国
2022
客户
工程
承包商
防护对象
Railway
腐蚀保护
GEOBRUGG SUPERCOATING
稳定的地区
3000 m²
边坡高度
20 m
边坡坡度从
80 ° - 85 °
博览会
North-East
情况

The project occurred over two phases, the first began in 2020 when BAM Ritchies was first approached to stabilise an area of unravelling on an existing shotcrete facing which was covering a chalk cutting. The site was precariously placed between a row of terraced houses on Stanford Lane and the operational train depot, part of Brighton Railway Station. 

Following completion of the emergency works and a further investigation, the decision was made to move forward and stabilise the majority of the 20 metres high 200 metres long chalk cutting with COWI acting as the designer. 

地質學

Chalk - Newhaven Chalk Formation

描述

The first stage of the solution involved emergency works to stabilise the area of unravelling, this included a small area of meshing and rock bolting as well as backfilling of the voided shotcrete facing using a thixotropic grout mix. 

The final engineered solution across the length of the slope, completed by BAM Ritchies in early 2022, included around 3000 square metres of TECCO G65/3 mesh with over 800 P33/50 spike plates installed and drainage paths also drilled. 

本地联系方式

Roger Moor
Roger Moor
Country Manager Ost- und Zentralschweiz, Liechtenstein
自然災害防護, Coastal Erosion Protection, 矿井/隧道
Geobrugg AG
Aachstrasse 11
8590 Romanshorn / 瑞士
René Müller
René Müller
Country Manager Kantone AG BE BL BS FR GE JU NE SO VD VS
自然災害防護, 矿井/隧道
Geobrugg AG
Industriestrasse 21
5200 Brugg / 瑞士
Alexander Bittendorfer
Alexander Bittendorfer
Global Project Manager Services
自然災害防護
Geobrugg AG
Aachstrasse 11
8590 Romanshorn / 瑞士
Isacco Toffoletto
Isacco Toffoletto
Ticino Country Manager
自然災害防護, 矿井/隧道
Geobrugg AG Ticino
Stabile Cometal, via Pizzante 7
6595 Riazzino / 瑞士