myGeobrugg
Scaling activities must take place at Bodenberg B21. In order to keep the road open, the road authorities had to select a system that protects both traffic from the falling rock and the road workers from the traffic. They required that the system is robust and quickly deployable.
The solution: 60 meters of homologated mobile debris fence (mDF350-2) while keeping one lane of the road open within two weeks of order. The installation took 4 hours to complete. It allows for the road to remain open during the entire works.