Селевые потоки и микросели - Olt Valley, km 239+500 - 246+500 - Rock 2015

GBE-1000A rockfall barrier protecting national road DN7

Селевые потоки и микросели - Olt Valley, km 239+500 - 246+500 - Rock 2015

GBE-1000A rockfall barrier base plate anchors drilling works

Селевые потоки и микросели - Olt Valley, km 239+500 - 246+500 - Rock 2015

Drilling flexible wire rope anchors for the GBE-1000A barrier

Селевые потоки и микросели - Olt Valley, km 239+500 - 246+500 - Rock 2015

One of the GBE-1000A rockfall barrier lines, completely installed

Селевые потоки и микросели - Olt Valley, km 239+500 - 246+500 - Rock 2015

GBE-1000A rockfall without border post - special solution for direct rock face connection

Селевые потоки и микросели - Olt Valley, km 239+500 - 246+500 - Rock 2015

Perfect solution containing passive GBE-1000A rockfall barrier and active slope stabilization with nailed TECCO® SYSTEM³

Селевые потоки и микросели - Olt Valley, km 239+500 - 246+500 - Rock 2015

Another line of GBE-1000A barrier with direct rock face connection

Селевые потоки и микросели - Olt Valley, km 239+500 - 246+500 - Rock 2015

Fully installed VX-060L debris flow barrier

Селевые потоки и микросели - Olt Valley, km 239+500 - 246+500 - Rock 2015

A short - only 22 m long - GBE-1000A barrier along national road DN7

 

Системы

 

Длина системы

20 m - 50 m

 

Год установки

2015

Ситуация

National road no. 7 (DN7) is one of the most important routes through the Carpathian Mountains, with heavy traffic. The Olt River runs parallel to the DN7 with high mountains, directly next to the road. In winter and spring rockfalls occur regularly. Also with unstable slopes, torrents and avalanches the risk of accidents was high. 

This project was originally developed with five concrete canopies for rockfall protection. Due to costs and other restrictions, a modern solution using high tensile steel wire was chosen. After further investigation, 23 dangerous areas were found and had to be protected using two types of protection systems: active and passive.

Описание

GBE rockfall barriers were provided as a passive protection at the following sectors:

1. km 240+454 - 240+510

GBE-1000

  • capacity: 1000 kJ
  • height: 5 m
  • length: 56 m

2. km 240+555 - 240+577

GBE-1000

  • capacity: 1000 kJ
  • height: 3 m
  • length: 22 m

3. km 242+453 - 242+457 (as a debrisflow barrier)

VX-060

  • height: 3 m
  • length: 8 m

 4. km 242+457 - 242+610

GBE-1000

  • capacity: 1000 kJ
  • height: 4 m
  • length: 30 m and 36 m

 5. km 242+859 - 242+940

GBE-1000

  • capacity: 1000 kJ
  • height: 4 m
  • length: 30 m

 

6. km 243+099 - 243+179

GBE-1000

  • capacity: 1000 kJ
  • height: 4 m
  • length: 30 m

See also the other projects of Olt Valley.

Страна / Регион

Румыния

Клиент

Compania Naţională de Administrare a Infrastructurii Rutiere (C.N.A.I.R.) – Directia Regionala de Drumuri si Poduri Craiova (D.R.D.P.)

Проектировщик

A.C. IRIMAT Cons S.R.L.

Подрядчик

S.C. VECTRA GROUP S.A.

Dahil olan diğer şirketler

Sachschische Bau GmbH Dresden Germany, Sibiu Branch

Защищаемый объект

Дорога

Защита от коррозии

Оцинковка, GEOBRUGG SUPERCOATING

Представитель в Вашем регионе

René Müller
   

René Müller

Country Manager Western Switzerland

Инженерная защита
Гидротехника
Горнодобывающая промышленность / Туннели
Monitoring
Геобругг АГ,Industriestrasse 21,5200 Brugg / Швейцария Country Manager Western Switzerland

Электронная почта

Olivia Sartorius
   

Olivia Sartorius

Project Manager Sales Eastern and Central Switzerland

Инженерная защита
Гидротехника
Горнодобывающая промышленность / Туннели
Monitoring
Геобругг АГ Project Manager Sales Eastern and Central Switzerland

Электронная почта

Isacco Toffoletto
   

Isacco Toffoletto

Country Manager Southern Switzerland

Инженерная защита
Гидротехника
Горнодобывающая промышленность / Туннели
Monitoring
Geobrugg AG Ticino,Stabile Cometal, via Pizzante 7,6595 Riazzino / Швейцария Country Manager Southern Switzerland

Электронная почта