In March 2021, a rockfall of around 15,000 tons occurred near Kestert. The track and the road underneath had to be closed.
After scaling and clearing works, the protective netting was installed. The nailings are between six and twelve meters long. Other at-risk sections were secured with SPIDER S3-130 and SPIDER S4-130.
독일
Feldhaus Bergbau GmbH & Co. KG, Karl-Heinz Schneider Baugeschäft GmbH, Schönberger Bau GmbH & Co. KG
Road, Railway
GEOBRUGG SUPERCOATING