Slope Stability - Cartagena Viaduct 2023

Rock block separating the bridge - stabilized with steel-wire mesh and spike plates

Slope Stability - Cartagena Viaduct 2023

SPIDER® S3-130 mesh and spike plates

Slope Stability - Cartagena Viaduct 2023

Re-vegetation at the foot of the rock

 
 

Year of installation

2023

Initial situation

The G-94-F highway links Cartagena with other cities on the central coast of Chile. The highway passes an over 40-meter-high bridge. A rock separates the two lanes of the bridge. This large rock fractured, and the gap began to expand, threatening the infrastructure and, thus, the connection between the cities.

The company GESVIAL is responsible for keeping the rock stable and the road safe by installing a stabilization system to stop the expansion of the opening.

Description

Today, the SPIDER® S3-130 system is stabilizing the rock. 
The rock’s volume is 18 cubic meters and weighs about 50 tons. It appears stable and sound, with a 10 mm crack opening and an inclination angle of 45°. The rock has not shown movements.

The system was installed with drilling anchors, spike plates, cable anchors, steel cables, and connection accessories.

Country/Region

Chile

Customer

Protected object

Road

Corrosion protection

GEOBRUGG SUPERCOATING

Your local contact

René Müller
   

René Müller

Country Manager Western Switzerland

Natural Hazards
Hydraulic Engineering
Mining / Tunnels
Geobrugg AG,Industriestrasse 21,5200 Brugg / Switzerland Country Manager Western Switzerland

E-Mail

Olivia Sartorius
   

Olivia Sartorius

Project Manager Sales Eastern and Central Switzerland

Natural Hazards
Hydraulic Engineering
Mining / Tunnels
Geobrugg AG Project Manager Sales Eastern and Central Switzerland

E-Mail

Alexander Bittendorfer
   

Alexander Bittendorfer

Project Manager Inspection Services

Natural Hazards
Monitoring
Geobrugg AG,Trucks via road 14 or 13 only!, Aachstrasse 11,8590 Romanshorn / Switzerland Project Manager Inspection Services

E-Mail

Isacco Toffoletto
   

Isacco Toffoletto

Country Manager Southern Switzerland

Natural Hazards
Hydraulic Engineering
Mining / Tunnels
Geobrugg AG Ticino,Via Brusada 5,6933 Muzzano / Switzerland Country Manager Southern Switzerland

E-Mail