Olt Valley, km 239+500 - 246+500 - Slope

Stabilizacja skarp - Olt Valley, km 239+500 - 246+500 - Slope 2015

A combination of two protection systems: active TECCO® SYSTEM³ is installed under the GBE-1000A rockfall barrier line providing passive protection

Stabilizacja skarp - Olt Valley, km 239+500 - 246+500 - Slope 2015

Superficial cleaning of the slope and drilling points stake-out

Stabilizacja skarp - Olt Valley, km 239+500 - 246+500 - Slope 2015

Drilling points stake-out in progress - visible national road DN7

Stabilizacja skarp - Olt Valley, km 239+500 - 246+500 - Slope 2015

Nails drilling directly through the high tensile mesh TECCO® 65/3

Stabilizacja skarp - Olt Valley, km 239+500 - 246+500 - Slope 2015

TECCO® SYSTEM³ installation - the high tensile mesh perfectly follows the slope morphology

Stabilizacja skarp - Olt Valley, km 239+500 - 246+500 - Slope 2015

Final positioning of the TECCO® SYSTEM³ splike plates type P33/40 and pre-tensioning of the mesh

Stabilizacja skarp - Olt Valley, km 239+500 - 246+500 - Slope 2015

Slope fully secured with TECCO® SYSTEM³

Stabilizacja skarp - Olt Valley, km 239+500 - 246+500 - Slope 2015

Another view of the fully stabilized slope

Stabilizacja skarp - Olt Valley, km 239+500 - 246+500 - Slope 2015

TECCO® SYSTEM³ almost invisible after installation - its open structure allows perfect drainage

 
 

Rok Instalacji / Montazu

2015

Sytuacja początkowa

National road no. 7 (DN7) is one of the most important routes through the Carpathian Mountains, with heavy traffic. The Olt River runs parallel to the DN7 with high mountains, directly next to the road. In winter and spring rockfalls occur regularly. Also with unstable slopes, torrents and avalanches the risk of accidents was high. 

This project was originally developed with five concrete canopies for rockfall protection. Due to costs and other restrictions, a modern solution using high tensile steel wire was chosen. After further investigation, 23 dangerous areas were found and had to be protected using two types of protection systems: active and passive.

Geologia

Along the whole section, mica and para gneiss appear in outcrops belonging to the series of the tail (the upper Proterozoic ante) and the local packet sandstone, covered at the top by diluvium deposit (dust, sand and gravel powder blocks).


Slopes (for the most part covered with forest) show inclinations of up to 60 - 80° and are strongly tectonized (kneading such, micro cracks) and continuous processes of disintegration. The angle of the rock packages varies between 30 - 55° (lower to higher sandstone and mica).

Opis zastosowanego rozwiazania

4200 m² of TECCO® System and 560 m² of SPIDER® System were installed together with nailing as an active protection measure on the following sectors:

1. km 240+421 - 240+441

TECCO® G65/3

  • stabilized area: 260 m²
  • slope height: 15 m
  • nail pattern: 2.20 x 2.20 m
  • nail type: GEWI 28
  • nail length: 3 m

2. km 240+441 - 240+467

SPIDER® S3-130

  • stabilized area: 540 m²
  • slope height: 18 m
  • nail distance: 2.50 m
  • nail type: GEWI 32
  • nail length: 3 m

3. km 240+510 - 240+555

TECCO® G65/3

  • stabilized area: 585 m²
  • slope height: 13 m
  • nail pattern: 2.50 x 2.50 m
  • nail type: GEWI 32
  • nail length: 3 m

4. km 242+457 - 240+610

TECCO® G65/3

  • stabilized area: 1377 m²
  • slope height: 10 m
  • nail pattern: 2.10 x 2.10 m
  • nail type: GEWI 32
  • nail length: 3 m

5. km 242+859 - 242+940

TECCO® G65/3

  • stabilized area: 640 m²
  • slope height: 13 m
  • nail pattern: 2.20 x 2.20 m
  • nail type: GEWI 32
  • nail length: 3 m

6. km 243+099 - 243+179

TECCO® G65/3

  • stabilized area: 1260 m²
  • slope height: 14 m
  • nail pattern: 2.20 x 2.20 m
  • nail type: GEWI 32
  • nail length: 3 m

See also the other projects of Olt Valley.

Kraj / Region

Rumunia

Inwestor

Compania Naţională de Administrare a Infrastructurii Rutiere (C.N.A.I.R.) – Directia Regionala de Drumuri si Poduri Craiova (D.R.D.P.)

Projektant

S.C. IRIMAT Cons S.R.L. - Bucharest

Wykonawca

S.C. VECTRA SERVICE S.R.L.

Inne przedsiębiorstwa

Sächsische Bau GmbH Dresden Germany, Sibiu Branch

Chroniony Objekt

Road

Ochrona przeciwerozyjna

GEOBRUGG SUPERCOATING

Osoba kontaktowa na miejscu

René Müller
   

René Müller

Country Manager Western Switzerland

Zagrożeniami naturalnymi
Nżynieria hydrauliczna
Kopalnie / Wydobycie / Tunel
Asset Management / Monitoring
Geobrugg AG,Trucks via road 14 or 13 only!, Aachstrasse 11,8590 Romanshorn / Szwajcaria Country Manager Western Switzerland

Formularz kontaktowy

Olivia Sartorius
   

Olivia Sartorius

Country Manager Eastern and Central Switzerland

Zagrożeniami naturalnymi
Nżynieria hydrauliczna
Kopalnie / Wydobycie / Tunel
Asset Management / Monitoring
Geobrugg AG Country Manager Eastern and Central Switzerland

Formularz kontaktowy

Isacco Toffoletto
   

Isacco Toffoletto

Country Manager Southern Switzerland

Zagrożeniami naturalnymi
Nżynieria hydrauliczna
Kopalnie / Wydobycie / Tunel
Asset Management / Monitoring
Geobrugg AG Ticino,Stabile Cometal, via Pizzante 7,6595 Riazzino / Szwajcaria Country Manager Southern Switzerland

Formularz kontaktowy