Ochrona przed obrywami skalnymi - Hagwood Cutting 2024

View of GBE-500A-R and approaching train

Ochrona przed obrywami skalnymi - Hagwood Cutting 2024

Eastern extent of the rockfall fence

Ochrona przed obrywami skalnymi - Hagwood Cutting 2024

Western extent of the rockfall fence

 

Zastosowane systemy

 

Dlugosc systemu od

- 55 m

 

Rok Instalacji / Montazu

2024

Sytuacja początkowa

The site is made up of a 6 - 15 metres high rock cutting comprised predominantly of sandstone adjacent to the railway line SPC8 in Belper, Derbyshire.

Since 2020, there have been three confirmed rockfall events, thankfully none of which infringed on track limits. Following a detailed geotechnical assessment of the site, which included rockfall modelling, it was found there was a moderate to high risk of rockfall across the site and it was recommended remediation measures be taken to mitigate future rockfall impacts.

Rockfall modelling indicated a maximum energy of 280 kJ of rockfall impact.

Opis zastosowanego rozwiazania

The chosen solution was a 2 metre high GBE-500A-R rockfall barrier, 55 metres in length and with a post spacing of 11metres.

The use of a GBE-AR barrier meant there were no upslope ropes within the system and thus saved time during the works via a reduced number of holes that needed to be drilled, compared to a GBE-500A rockfall barrier.

Once the fence arrived, Geobrugg conducted a toolbox talk on-site, discussing the steps and common pitfalls during installation.

Initial works were carried out by QTS (contractor) on night shifts, and the final completion of the fence construction the following week on day shifts. Once the fence was completed a CONSIS-trained professional (Geobrugg) undertook a final acceptance inspection of the rockfall fence. 

Kraj / Region

Zjednoczone Królestwo

Inwestor

QTS

Projektant

Wykonawca

QTS

Chroniony Objekt

Railway

Ochrona przeciwerozyjna

GEOBRUGG SUPERCOATING

Osoba kontaktowa na miejscu

René Müller
   

René Müller

Country Manager Western Switzerland

Zagrożeniami naturalnymi
Nżynieria hydrauliczna
Kopalnie / Wydobycie / Tunel
Geobrugg AG,Industriestrasse 21,5200 Brugg / Szwajcaria Country Manager Western Switzerland

Formularz kontaktowy

Olivia Sartorius
   

Olivia Sartorius

Project Manager Sales Eastern Switzerland

Zagrożeniami naturalnymi
Nżynieria hydrauliczna
Kopalnie / Wydobycie / Tunel
Geobrugg AG Project Manager Sales Eastern Switzerland

Formularz kontaktowy

Alexander Bittendorfer
   

Alexander Bittendorfer

Project Manager Inspection Services

Zagrożeniami naturalnymi
Geobrugg AG,Trucks via road 14 or 13 only!, Aachstrasse 11,8590 Romanshorn / Szwajcaria Project Manager Inspection Services

Formularz kontaktowy

Isacco Toffoletto
   

Isacco Toffoletto

Country Manager Southern Switzerland

Zagrożeniami naturalnymi
Nżynieria hydrauliczna
Kopalnie / Wydobycie / Tunel
Geobrugg AG Ticino,Via Brusada 5,6933 Muzzano / Szwajcaria Country Manager Southern Switzerland

Formularz kontaktowy