Sytuacja początkowa

Planned extensions to the sandstone, Gritstone quarry required the extraction of overburden. Materials had the potential to travel down the outer edge of the site, down to the A44 road.

Key Geosolutions undertook rockfall analysis and calculated that a 500kJ and 3 metres high rockfall system would be required.

Opis zastosowanego rozwiazania

Derbyshire Geotechnical contacted Geobrugg for advice on system types best suited for this location.

After an initial site visit, it was agreed that the GBE-500A would be the best option as the reduced post weight over that of the GBE-500A-R allowed for easier installation due to the limited access routes to the location.

The 100 m long system with post spacings of 10 m (11 posts) was secured with 2nr 4 m long threaded bars. Upslope and lateral anchors were 6 m long threaded bars fitted with Geobrugg flexheads.

Kraj / Region

Zjednoczone Królestwo

Inwestor

Tarmac Ltd

Projektant

Key Geosolutions

Wykonawca

Derbyshire Geotechnical

Inne przedsiębiorstwa

None

Chroniony Objekt

Mine / Quarry

Osoba kontaktowa na miejscu

René Müller
   

René Müller

Country Manager Kantone AG BE BL BS FR GE JU NE SO VD VS

Zagrożeniami naturalnymi
Nżynieria hydrauliczna
Kopalnie / Wydobycie / Tunel
Geobrugg AG,Industriestrasse 21,5200 Brugg / Szwajcaria Country Manager Kantone AG BE BL BS FR GE JU NE SO VD VS

Formularz kontaktowy

Olivia Sartorius
   

Olivia Sartorius

Zagrożeniami naturalnymi
Nżynieria hydrauliczna
Kopalnie / Wydobycie / Tunel
Geobrugg AG

Formularz kontaktowy

Alexander Bittendorfer
   

Alexander Bittendorfer

Project Manager Inspection Services

Zagrożeniami naturalnymi
Geobrugg AG,Trucks via road 14 or 13 only!, Aachstrasse 11,8590 Romanshorn / Szwajcaria Project Manager Inspection Services

Formularz kontaktowy

Isacco Toffoletto
   

Isacco Toffoletto

Zagrożeniami naturalnymi
Nżynieria hydrauliczna
Kopalnie / Wydobycie / Tunel
Geobrugg AG Ticino,Via Brusada 5,6933 Muzzano / Szwajcaria

Formularz kontaktowy