The Ten West Link project is a new power project from Southern Arizona & California. The project goes across the Eagletail Mountains & Wildreness, where transmission line towers will be built.

説明

Geobrugg was tasked with providing ten GBE-100A-R rockfall barriers to protect ten transmission line towers that will be built. The barriers are three meters high with a total length of 230 meters.

These barriers will protect personnel, roadway and future transmission lines. This particular transmission line will span 125 miles connecting Arizona and California, improving transmission system efficiency and reliability.

Thank you Adams Contracting for the pictures. 

国名

アメリカ合衆国

顧客名

落札者

保護対象

道路, インフラ

腐食防止

亜鉛めっき

担当者の連絡先

René Müller
   

René Müller

Country Manager Western Switzerland

自然災害防護
Hydraulic Engineering
鉱山/トンネル
モニタリングサービス
Geobrugg AG,Industriestrasse 21,5200 Brugg / スイス Country Manager Western Switzerland

お問い合わせフォーム

Olivia Sartorius
   

Olivia Sartorius

Project Manager Sales Eastern and Central Switzerland

自然災害防護
Hydraulic Engineering
鉱山/トンネル
モニタリングサービス
Geobrugg AG Project Manager Sales Eastern and Central Switzerland

お問い合わせフォーム

Matthias Denk, Msc. Env. Eng.
 

Matthias Denk

自然災害防護
Hydraulic Engineering
Geobrugg AG,Aachstrasse 11,8590 Romanshorn / スイス , Msc. Env. Eng.

お問い合わせフォーム

Isacco Toffoletto
   

Isacco Toffoletto

Country Manager Southern Switzerland

自然災害防護
Hydraulic Engineering
鉱山/トンネル
モニタリングサービス
Geobrugg AG Ticino,Via Brusada 5,6933 Muzzano / スイス Country Manager Southern Switzerland

お問い合わせフォーム