Stati Uniti
Stati Uniti

myGeobrugg

Timber Loading Gare Porrentruy, Ajoie

Protezione dagli impatti - Timber Loading Gare Porrentruy, Ajoie 2021

Passenger trains can now pass the site without danger; the mesh separates passing trains from the timber loading station

Protezione dagli impatti - Timber Loading Gare Porrentruy, Ajoie 2021

The transparent protective fence looks significantly lighter than, for example, a concrete wall

Protezione dagli impatti - Timber Loading Gare Porrentruy, Ajoie 2021

Railroad operation could be maintained during the assembly

Protezione dagli impatti - Timber Loading Gare Porrentruy, Ajoie 2021

The mesh is tensioned on supporting ropes at the bottom and top

Protezione dagli impatti - Timber Loading Gare Porrentruy, Ajoie 2021

Detail: connection of the mesh elements

 

Sistemi

Soluzioni speciali

 

Anno di installazione

2021

Situazione iniziale

Among other things, the rail operator Chemins de Fer du Jura loads wood onto freight cars. There was a risk of tree trunks or small parts falling onto the passenger transport line during loading.

Descrizione

Geobrugg was contracted to develop a solution to protect the danger zone.

In the first phase, one-meter-high concrete bases and steel girders dimensioned by Geobrugg were prefabricated and installed by the client. Geobrugg then installed the steel cables and tensioned the mesh (G80/4).

The distance between the supports is three meters; the total length is 39 meters.

Oggetto protetto

Ferrovia

Progettazione:

Il contatto locale

Ivo Naef
 

Ivo Naef

Sales Manager Safety Solutions

DPC per l’industria e l’edilizia
Geobrugg AG,Aachstrasse 11,8590 Romanshorn / Svizzera Sales Manager Safety Solutions

E-mail