Consolidamento di versanti - Dartford Greenhithe 2022

Aerial view of final installation

Consolidamento di versanti - Dartford Greenhithe 2022

TECCO installation

Consolidamento di versanti - Dartford Greenhithe 2022

Smaller first section of works

 

Anno di installazione

2022

Situazione iniziale

Following the instability of several areas of chalk cliff face adjacent to London Road, RSK was appointed as a designer to assess the slope instability and form a remediation strategy for the area. Risk areas were the footpath running along the base of the site as well as London Road atop the cliff with undermining of the road a possibility if protective measures were not put in place.

Geologia

Lewes Nodular Chalk Formation

Descrizione

The site was divided up into three sections, the first was a smaller mound of limestone approximately 8 metres in height, 15 metres wide and made up of three visible sides, rock bolted and meshed using TECCO G65/3 and TECCO GREEN. 

The main section of works comprised the cliff directly below London Road, the chalk in this area was around 20 metres in height, with the section running almost 100 metres. Drilling conditions on site were generally good with no flint bands present in the limestone, and a combination of grout and air flush was used. In total 630 holes were drilled across the site.

CAN Ltd was appointed as the contractor responsible for installation of the protective measures

Paese / Regione

Regno Unito

Cliente

Progettazione:

RSK

Contraente:

Oggetto protetto

Strada, Zona residenziale

Protezione dalla corrosione

GEOBRUGG SUPERCOATING

Il contatto locale

René Müller
   

René Müller

Country Manager Western Switzerland

Sistemi contro il dissesto idrogeologico
Ingegneria idraulica
Miniera / Gallerie
Geobrugg AG,Industriestrasse 21,5200 Brugg / Svizzera Country Manager Western Switzerland

E-mail

Olivia Sartorius
   

Olivia Sartorius

Project Manager Sales Eastern Switzerland

Sistemi contro il dissesto idrogeologico
Ingegneria idraulica
Miniera / Gallerie
Geobrugg AG Project Manager Sales Eastern Switzerland

E-mail

Alexander Bittendorfer
   

Alexander Bittendorfer

Project Manager Inspection Services

Sistemi contro il dissesto idrogeologico
Sistema di monitoraggio da remoto
Geobrugg AG,Trucks via road 14 or 13 only!, Aachstrasse 11,8590 Romanshorn / Svizzera Project Manager Inspection Services

E-mail

Isacco Toffoletto
   

Isacco Toffoletto

Country Manager Southern Switzerland

Sistemi contro il dissesto idrogeologico
Ingegneria idraulica
Miniera / Gallerie
Geobrugg AG Ticino,Via Brusada 5,6933 Muzzano / Svizzera Country Manager Southern Switzerland

E-mail