Estabilización de taludes - Olt Valley, km 239+500 - 246+500 - Slope 2015

A combination of two protection systems: active TECCO® SYSTEM³ is installed under the GBE-1000A rockfall barrier line providing passive protection

Estabilización de taludes - Olt Valley, km 239+500 - 246+500 - Slope 2015

Superficial cleaning of the slope and drilling points stake-out

Estabilización de taludes - Olt Valley, km 239+500 - 246+500 - Slope 2015

Drilling points stake-out in progress - visible national road DN7

Estabilización de taludes - Olt Valley, km 239+500 - 246+500 - Slope 2015

Nails drilling directly through the high tensile mesh TECCO® 65/3

Estabilización de taludes - Olt Valley, km 239+500 - 246+500 - Slope 2015

TECCO® SYSTEM³ installation - the high tensile mesh perfectly follows the slope morphology

Estabilización de taludes - Olt Valley, km 239+500 - 246+500 - Slope 2015

Final positioning of the TECCO® SYSTEM³ splike plates type P33/40 and pre-tensioning of the mesh

Estabilización de taludes - Olt Valley, km 239+500 - 246+500 - Slope 2015

Slope fully secured with TECCO® SYSTEM³

Estabilización de taludes - Olt Valley, km 239+500 - 246+500 - Slope 2015

Another view of the fully stabilized slope

Estabilización de taludes - Olt Valley, km 239+500 - 246+500 - Slope 2015

TECCO® SYSTEM³ almost invisible after installation - its open structure allows perfect drainage

 
 

Año de instalación

2015

Situación inicial

National road no. 7 (DN7) is one of the most important routes through the Carpathian Mountains, with heavy traffic. The Olt River runs parallel to the DN7 with high mountains, directly next to the road. In winter and spring rockfalls occur regularly. Also with unstable slopes, torrents and avalanches the risk of accidents was high. 

This project was originally developed with five concrete canopies for rockfall protection. Due to costs and other restrictions, a modern solution using high tensile steel wire was chosen. After further investigation, 23 dangerous areas were found and had to be protected using two types of protection systems: active and passive.

Geología

Along the whole section, mica and para gneiss appear in outcrops belonging to the series of the tail (the upper Proterozoic ante) and the local packet sandstone, covered at the top by diluvium deposit (dust, sand and gravel powder blocks).


Slopes (for the most part covered with forest) show inclinations of up to 60 - 80° and are strongly tectonized (kneading such, micro cracks) and continuous processes of disintegration. The angle of the rock packages varies between 30 - 55° (lower to higher sandstone and mica).

Descripción

4200 m² of TECCO® System and 560 m² of SPIDER® System were installed together with nailing as an active protection measure on the following sectors:

1. km 240+421 - 240+441

TECCO® G65/3

  • stabilized area: 260 m²
  • slope height: 15 m
  • nail pattern: 2.20 x 2.20 m
  • nail type: GEWI 28
  • nail length: 3 m

2. km 240+441 - 240+467

SPIDER® S3-130

  • stabilized area: 540 m²
  • slope height: 18 m
  • nail distance: 2.50 m
  • nail type: GEWI 32
  • nail length: 3 m

3. km 240+510 - 240+555

TECCO® G65/3

  • stabilized area: 585 m²
  • slope height: 13 m
  • nail pattern: 2.50 x 2.50 m
  • nail type: GEWI 32
  • nail length: 3 m

4. km 242+457 - 240+610

TECCO® G65/3

  • stabilized area: 1377 m²
  • slope height: 10 m
  • nail pattern: 2.10 x 2.10 m
  • nail type: GEWI 32
  • nail length: 3 m

5. km 242+859 - 242+940

TECCO® G65/3

  • stabilized area: 640 m²
  • slope height: 13 m
  • nail pattern: 2.20 x 2.20 m
  • nail type: GEWI 32
  • nail length: 3 m

6. km 243+099 - 243+179

TECCO® G65/3

  • stabilized area: 1260 m²
  • slope height: 14 m
  • nail pattern: 2.20 x 2.20 m
  • nail type: GEWI 32
  • nail length: 3 m

See also the other projects of Olt Valley.

País / Región

Rumanía

Cliente

Compania Naţională de Administrare a Infrastructurii Rutiere (C.N.A.I.R.) – Directia Regionala de Drumuri si Poduri Craiova (D.R.D.P.)

Ingeniería

S.C. IRIMAT Cons S.R.L. - Bucharest

Subcontratista

S.C. VECTRA SERVICE S.R.L.

Otras empresas participantes

Sächsische Bau GmbH Dresden Germany, Sibiu Branch

Objeto protegido

Carretera

Protección contra la corrosión

GEOBRUGG SUPERCOATING

Su contacto local

René Müller
   

René Müller

Country Manager Western Switzerland

Protección contra riesgos naturales
Ingeniería hidráulica
Minería / Túneles
Sistema de Monitoreo
Geobrugg AG,Trucks via road 14 or 13 only!, Aachstrasse 11,8590 Romanshorn / Suiza Country Manager Western Switzerland

Correo electrónico

Olivia Sartorius
   

Olivia Sartorius

Country Manager Eastern and Central Switzerland

Protección contra riesgos naturales
Ingeniería hidráulica
Minería / Túneles
Sistema de Monitoreo
Geobrugg AG Country Manager Eastern and Central Switzerland

Correo electrónico

Isacco Toffoletto
   

Isacco Toffoletto

Country Manager Southern Switzerland

Protección contra riesgos naturales