Borusan EnBW

Ispir Erzurum, Turkey
2019
Customer
Borusan EnBW
Engineering
Geobrugg AG
Contractor
Artusa Geohazard
Protected object
Other
System height
6.0 m
System length
15 m
Corrosion protection
GEOBRUGG SUPERCOATING®
Number of barriers
1
Retention capacity
3000 m³
Initial situation

At the hydro power plant infrastructure in 2011 and 2017 torrents brought down debris and clogged culverts of the draining system.  Around 5'000 m³ of debris damaged the HPP area.

Description

At the ideal place for this debris flow barrier, there also is an area for debris material nearby. The system is a V-shaped, 6 meters high barrier (VX160-H6) with 8 meters deep wire rope anchors.

Your local contact

Kevin H. Coyle
Kevin H. Coyle
Regional Manager Northeast
Natural Hazards
Geobrugg North America, LLC
3 Beaudet Terr
Columbia CT 06237 / USA
Phone +1 860 377 3230

Contact form

Saleh Feidi
Saleh Feidi
Regional Manager California
Natural Hazards
Geobrugg North America, LLC
8921 Emperor Ave.
San Gabriel, California 91775 / USA
Phone +1 909 706 8964

Contact form

John Kalejta
John Kalejta
Regional Manager Central US
Natural Hazards
Geobrugg North America, LLC
3215 67th Avenue Pl
Greeley CO 80634 / USA
Phone +1 505 220 1404

Contact form

Bob Lyne
Bob Lyne
Regional Manager Southeast
Natural Hazards
Geobrugg North America, LLC
8004 Windspray Drive
Summerfield NC 27358 / USA
Phone +1 336 337 0945

Contact form

Pierce Runnels, Civil Engineer
Pierce Runnels, Civil Engineer
General Manager Geobrugg North America
Natural Hazards
Geobrugg North America, LLC
22 Centro Algodones
Phone +1 505 771 4080
Mobile +1 505 400 0796

Contact form

Tim Shevlin
Tim Shevlin
Sales Director
Natural Hazards
Geobrugg North America, LLC
4676 Commercial St. SE, PMB 174
Salem OR 97302 / USA
Phone +1 503 423 7258

Contact form