Böschungsstabilisierung - Wellards Way 2021

The slope following installation

Böschungsstabilisierung - Wellards Way 2021

Site visit 20th October 2020

Böschungsstabilisierung - Wellards Way 2021

Site visit 19th October 2021 with revegation

 

Installationsjahr

2021

Ausgangslage

Due to recent bad weather, there became a hazard of chalk blocks coming loose from the slope above and falling onto the zig-zagging footpath below. The footpath provides the only point of access for crossing the existing railway (directly south) to Shakespeare Beach, and it was key that the route was made safe for public use.

Geologie

New Pit Chalk Formation - a chalk of the Cretaceous Period.

Massnahme

Following a visit to the site in October 2020, we worked with the contractor, South East Abseiling, to find an appropriate solution for the problem. Due to the site’s proximity to the sea, a stainless steel mesh was recommended to ensure the highest degree of corrosion protection.

We supplied TECCO STAINLESS G65/3 and TECMAT and stainless steel P33/40 spike plates to ensure stablisation and revegetation of the existing slope. We maintained close contact with the contractor during the works, always on hand to answer technical queries related to installation and performance of our system. In particular, we advised the appropriate method of installation for TECMAT beneath TECCO STAINLESS G65/3 to ensure there was no contamination and subsequent degradation of the corrosion protection provided by the stainless steel mesh.
The result was a tidy installation and successful slope stablisation. A follow-up site visit was undertaken in October 2021, showing beginning revegetation.

Kunde

Ausführende Firma

Geschützte Objekte

Eisenbahn, Touristische Infrastruktur

Korrosionsschutz

INOX / STAINLESS

Ansprechpartner

Kevin H. Coyle
 

Kevin H. Coyle

Regional Manager Northeast

Naturgefahren
Uferschutz/Wasserbau
Geobrugg North America, LLC,3 Beaudet Terr,Columbia CT 06237 / USA Regional Manager Northeast

E-Mail

Saleh Feidi
 

Saleh Feidi

Regional Manager California

Naturgefahren
Uferschutz/Wasserbau
Geobrugg North America, LLC,8921 Emperor Ave.,San Gabriel, California 91775 / USA Regional Manager California

E-Mail

John Kalejta
 

John Kalejta

Regional Manager Central US

Naturgefahren
Uferschutz/Wasserbau
Geobrugg North America, LLC,3215 67th Avenue Pl,Greeley CO 80634 / USA Regional Manager Central US

E-Mail

Bob Lyne
 

Bob Lyne

Regional Manager Southeast

Naturgefahren
Uferschutz/Wasserbau
Geobrugg North America, LLC,8004 Windspray Drive,Summerfield NC 27358 / USA Regional Manager Southeast

E-Mail

Pierce Runnels, Civil Engineer
   

Pierce Runnels

General Manager Geobrugg North America

Naturgefahren
Geobrugg North America, LLC,22 Centro Algodones,NM 87001 Algodones / USA , Civil Engineer General Manager Geobrugg North America

E-Mail

Tim Shevlin
 

Tim Shevlin

Sales Director

Naturgefahren
Geobrugg North America, LLC,Salem OR 97302 / USA Sales Director

E-Mail