Steinschlagschutz - Hagwood Cutting 2024

View of GBE-500A-R and approaching train

Steinschlagschutz - Hagwood Cutting 2024

Eastern extent of the rockfall fence

Steinschlagschutz - Hagwood Cutting 2024

Western extent of the rockfall fence

 

Systeme

 

Systemlänge

- 55 m

 

Installationsjahr

2024

Ausgangslage

The site is made up of a 6 - 15 metres high rock cutting comprised predominantly of sandstone adjacent to the railway line SPC8 in Belper, Derbyshire.

Since 2020, there have been three confirmed rockfall events, thankfully none of which infringed on track limits. Following a detailed geotechnical assessment of the site, which included rockfall modelling, it was found there was a moderate to high risk of rockfall across the site and it was recommended remediation measures be taken to mitigate future rockfall impacts.

Rockfall modelling indicated a maximum energy of 280 kJ of rockfall impact.

Massnahme

The chosen solution was a 2 metre high GBE-500A-R rockfall barrier, 55 metres in length and with a post spacing of 11metres.

The use of a GBE-AR barrier meant there were no upslope ropes within the system and thus saved time during the works via a reduced number of holes that needed to be drilled, compared to a GBE-500A rockfall barrier.

Once the fence arrived, Geobrugg conducted a toolbox talk on-site, discussing the steps and common pitfalls during installation.

Initial works were carried out by QTS (contractor) on night shifts, and the final completion of the fence construction the following week on day shifts. Once the fence was completed a CONSIS-trained professional (Geobrugg) undertook a final acceptance inspection of the rockfall fence. 

Land/Region

Vereinigtes Königreich (UK)

Kunde

QTS

Planer

Ausführende Firma

QTS

Geschützte Objekte

Eisenbahn

Korrosionsschutz

GEOBRUGG SUPERCOATING

Ansprechpartner

René Müller
   

René Müller

Country Manager Western Switzerland

Naturgefahren
Uferschutz/Wasserbau
Minen / Bergbau / Tunnel
Geobrugg AG,Industriestrasse 21,5200 Brugg / Schweiz Country Manager Western Switzerland

E-Mail

Olivia Sartorius
   

Olivia Sartorius

Project Manager Sales Eastern Switzerland

Naturgefahren
Uferschutz/Wasserbau
Minen / Bergbau / Tunnel
Geobrugg AG Project Manager Sales Eastern Switzerland

E-Mail

Alexander Bittendorfer
   

Alexander Bittendorfer

Project Manager Inspection Services

Naturgefahren
Geobrugg AG,Trucks via road 14 or 13 only!, Aachstrasse 11,8590 Romanshorn / Schweiz Project Manager Inspection Services

E-Mail

Isacco Toffoletto
   

Isacco Toffoletto

Country Manager Southern Switzerland

Naturgefahren
Uferschutz/Wasserbau
Minen / Bergbau / Tunnel
Geobrugg AG,Via Brusada 5,6933 Muzzano / Schweiz Country Manager Southern Switzerland

E-Mail