USA
USA

myGeobrugg

Eastside Catchments Gibraltar

Steinschlagschutz - Eastside Catchments Gibraltar 2017

RXE-5000 rockfall barrier - 7 m high and 40 m long spectacular structure. View from up slope after completion of phase 1

Steinschlagschutz - Eastside Catchments Gibraltar 2017

RXE-5000 rockfall barrier - 7 m high and 40 m long installation process. View from up slope at the end of Phase 1

Steinschlagschutz - Eastside Catchments Gibraltar 2017

RXE-5000 separation post to connect the next phase of the project: visible transmission ropes and U-brake elements

Steinschlagschutz - Eastside Catchments Gibraltar 2017

CAN Geotechnical IRATA (Industrial Rope Access Trade Association) operatives pulling the ringnet panels to meet ready for connecting together with shackles

Steinschlagschutz - Eastside Catchments Gibraltar 2017

RXE-5000 rockfall barrier ring net panels being disconnected from the posts and banding being cut off ring nets

Steinschlagschutz - Eastside Catchments Gibraltar 2017

Post and mesh panels were lifted into position by crane. Visible the old small and insufficient barriers being replaced by the RXE-5000

Steinschlagschutz - Eastside Catchments Gibraltar 2017

RXE-5000 rockfall barrier border post tensioning of the top support ropes to the anchor blocks. Visible scale of rockfall danger behind the barrier

Steinschlagschutz - Eastside Catchments Gibraltar 2017

Another view of the RXE-5000 rockfall barrier installation during phase 1

Steinschlagschutz - Eastside Catchments Gibraltar 2017

RXE-5000 rockfall barrier post base showing running wheel attached and one running wheel loose for connection. This unique technology protects ropes and allows their almost frictionless movement

Steinschlagschutz - Eastside Catchments Gibraltar 2017

View of the completed RXE-5000 rockfall barrier after completion of phase 2

Steinschlagschutz - Eastside Catchments Gibraltar 2017

Ring nets and ropes on the RXE-5000. Visible secondary mesh behind ring net

Steinschlagschutz - Eastside Catchments Gibraltar 2017

End post of the RXE-5000

Steinschlagschutz - Eastside Catchments Gibraltar 2017

Lateral anchors, note the special casing around the top of the bar.

Steinschlagschutz - Eastside Catchments Gibraltar 2017

View of the completed RXE-5000 at the end of phase 2

Steinschlagschutz - Eastside Catchments Gibraltar 2017

View of the completed RXE-5000 at the end of phase 2

 

Systeme

 

Systemlänge

88 m

 

Installationsjahr

2017

Ausgangslage

Following rockfall in 2015 Golder Associates undertook a design for rockfall mitigation measures to protect the road and residential properties below. The detailed rockfall analysis showed a requirement for protection from a 5000 kJ impact with a system height of 7 m.

Massnahme

In December 2016 CAN Geotechnical were awarded the project to complete phase 1 of the works, a 40 m long and 7 m high 5000 kJ rockfall barrier. We supplied a RXE-5000 barrier. To enable future works to be completed more easily and without deconstructing the existing fence, we provided a solution for the end post to alllow for this.

Over several years and many projects Geobrugg has worked with both Golders Associates and CAN Geotechncial and a good relationship has developed.  This enabled all of the involved parties to work together to find a cost effective and buildable solution. 

The ground conditions on the eastside catchments are well known and extremly difficut to work within. To enable the works to be completed CAN Geotechnical had to carry out lots of temporary works and to use enlarged concrete bases for the fence posts.  Additionally CAN Geotechnical opted to terminate all ground anchors into reinforced concrete bases with wire rope eyes protruding for connection to Geobrugg U-brakes.

In Januray 2018 CAN returned to site to instal the remaining 48m of barrier.  The customised solution installed on the previous section worked perfectly enabling a smooth instalation and transition between the two barriers.

For this phase of works CAN built upon their knowledge of the ground conditions encountered last time and in conjunction with the designer were able to use a more conventional anchoring solution avoiding the need for the large concrete foundations beams and the temporary soil nailing required in the previous phase. This was no easy task however as it required drilling with a 115mm bit to install R51 Hollow bar, with the requirement to install permanent casing in the upper part to provide extra stability.

Kunde

Government Of Gibraltar

Ausführende Firma

CAN Geotechnical Ltd.

Geschützte Objekte

Strasse, Touristische Infrastruktur, Wohngebiet, Infrastruktur

Korrosionsschutz

Verzinkt, GEOBRUGG SUPERCOATING

Planer

Golder Associates

Ansprechpartner

Kevin H. Coyle
 

Kevin H. Coyle

Regional Manager Northeast

Naturgefahren
Uferschutz/Wasserbau
Geobrugg North America, LLC,3 Beaudet Terr,Columbia CT 06237 / USA Regional Manager Northeast

E-Mail

Saleh Feidi
 

Saleh Feidi

Regional Manager California

Naturgefahren
Uferschutz/Wasserbau
Geobrugg North America, LLC,8921 Emperor Ave.,San Gabriel, California 91775 / USA Regional Manager California

E-Mail

John Kalejta
 

John Kalejta

Regional Manager Central US

Naturgefahren
Uferschutz/Wasserbau
Geobrugg North America, LLC,3215 67th Avenue Pl,Greeley CO 80634 / USA Regional Manager Central US

E-Mail

Bob Lyne
 

Bob Lyne

Regional Manager Southeast

Naturgefahren
Uferschutz/Wasserbau
Geobrugg North America, LLC,8004 Windspray Drive,Summerfield NC 27358 / USA Regional Manager Southeast

E-Mail

Pierce Runnels, Civil Engineer
   

Pierce Runnels

General Manager Geobrugg North America

Naturgefahren
Geobrugg North America, LLC,22 Centro Algodones,NM 87001 Algodones / USA , Civil Engineer General Manager Geobrugg North America

E-Mail

Tim Shevlin
 

Tim Shevlin

Sales Director

Naturgefahren
Geobrugg North America, LLC,Salem OR 97302 / USA Sales Director

E-Mail